DPA appointed IIT Madras on a nomination basis to prepare the DPR for Multipurpose Cargo Berth No. 17 at Kandla. The 12 March 2025 work order set INR 15 million plus GST and an 18 March start. Scope covers field review, CWPRS modelling, berth and approach design, heavy-cargo handling, dredging, reclamation, mooring, back-up yard, utilities, quantities and estimates. Later DPA records still place the project in owner-side development; no construction or PPP award is public.
Project signal
Design in India
Current statusDPR work started in March 2025; no construction RFP, PPP award, concessionaire or works contractor is verifiedSource confidenceConfirmed
Location
India / Asia Pacific
Segment
Port infrastructure
Status
DPR work started in March 2025; no construction RFP, PPP award, concessionaire or works contractor is verified / Confirmed
Last checked
1 August 2026
Coverage
Related sectors
Port infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
Deendayal Port Authority
Delivery parties
Indian Institute of Technology Madras - DPR consultant; principal investigator S Nallayarasu, Construction concessionaire or works contractor - no RFP or award verified by 1 August 2026
Contract route
DPA appointed IIT Madras on a nomination basis for the DPR. A later DPA technical-adviser tender listed development of Berth 17 on PPP mode among projects under approval, but that indicative list is not a PPP tender or concession award. Downstream procurement remains open.
Execution window
DPA directed the consultancy to start on 18 March 2025. IIT Madras records project IC24251616OEDEEN008228 from 13 March to 12 September 2025. The ledger close date belongs to the consultancy record and does not prove owner acceptance of the DPR or completion of any construction.
Works package
Prepare the inception and preliminary reports; collect field and soil data; assess wave, current and wind conditions; support final berth and back-up-yard siting; review borehole data; develop the CWPRS mathematical and siltation model; select jetty and approach arrangements for vessels carrying large wind-turbine and other cargo; evaluate mobile, rail-mounted and other heavy-cargo equipment; design marine structures, reclamation, shore protection, dredging layout, mooring, fire-fighting, utilities, berth systems and back-up yard; and prepare drawings, bills of quantities and estimates.
Marine interfaces
The project must connect a new cargo berth and approach to Kandla's working creek environment. Bathymetry, sedimentation, berth geometry, manoeuvring, dredging, reclamation, shore protection, geotechnical design, mooring loads, fenders, bollards, utilities and heavy-cargo transfer all sit inside the DPR boundary. DPA's work order says it will approach CWPRS for the mathematical study with berth data and drawings supplied by IIT Madras.
Commercial evidence boundary
DPA's accepted consultancy fee is INR 15 million plus GST. IIT Madras records a sanctioned value of INR 17.7 million for the same project, which appears to reflect the fee with tax rather than a different construction package. Neither amount is berth-construction capex, a PPP investment commitment or an awarded works price.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
The DPR assignment entered its instructed work period
IIT Madras began the owner-side engineering phase covering site appraisal, modelling, marine structures, dredging, reclamation, berth systems and cost preparation. Construction procurement remained outside the appointment.
The nomination-basis appointment fixed an INR 15 million fee plus GST and defined the engineering package, while leaving the eventual PPP or works route, contractor and construction price open.