The movable Lammebrug replacement crosses the Rijn-Schiekanaal in Leiden within the province-led N206 Europaweg contract. Dated contractor documents distinguish basement, support, bank and cable workfronts.
Marine infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
Province of Zuid-Holland
Delivery parties
Boskalis Nederland
Contract route
N206 Europaweg design-and-construct package: provincial intention-to-award decision in December 2023, design-team definitive-award announcement in February 2024. No separately priced bridge marine award identified.
Execution window
Contractor August 2026 bulletin announces September-October foundation/bank sequence and a later September cable-crossing window; these are planned dates, not accepted work or a commissioning deadline.
Works package
Replacement movable bridge basement, in-water central support foundations, navigation protection, bank sheet piles and underwater power/data crossing. Other N206 bridges and road elements remain distinct.
Marine interfaces
Weekday passage restrictions and a separate continuous cable-crossing closure interact with in-water workfront access. Longer possible working hours do not themselves alter navigation closure hours. The schematic is not a navigation notice.
Commercial evidence boundary
The operating connection and foundations require different access interfaces within a wider transport package. A contractor programme does not establish a new marine contract, subcontract allocation, selected vessel fleet or completed installation.
Contract and delivery chain
Work packages and named roles
Published scope, named parties and supporting evidence for each workstream.
Bridge foundations
Basement, central support and bank works
Named party
Boskalis Nederland
Evidence status
Confirmed
Source position
Contractor reports August concrete placement and schedules separate in-water workfronts; quantities and acceptance not confirmed. Source
Operating connection
Underwater power/data crossing
Named party
Boskalis Nederland
Evidence status
Confirmed
Source position
Dedicated later-September window announced, not confirmed installed or tested. Source
Evidence gap
What remains unverified
Outstanding evidence
Reported installation and testing for the control connection
Final bridge permission and acceptance records
Dated navigation arrangements for separate workfronts
Foundation quantities and identified marine equipment