Project record

Lammebrug in-water replacement and operating-cable interface

Participation
Not assessed
Project facts checked

Contractor reports basement concrete placement and announces further foundation/cable works; final acceptance and commissioning unconfirmed

Project sources

The movable Lammebrug replacement crosses the Rijn-Schiekanaal in Leiden within the province-led N206 Europaweg contract. Dated contractor documents distinguish basement, support, bank and cable workfronts.

Lammebrug Boskalis N206 scope graphic distinguishing Rijn-Schiekanaal bridge marine works from Trekvlietbrug and Knotterpolderbrug

IMWO original N206 bridge-package diagram from dated project-team and official permit documents; no geography or price split implied

Location

Netherlands / Europe

Segment

Marine infrastructure

Phase

Construction / Confirmed

Last checked

5 September 2026

Coverage

Related sectors

Marine infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Province of Zuid-Holland
Delivery parties
Boskalis Nederland
Contract route
N206 Europaweg design-and-construct package: provincial intention-to-award decision in December 2023, design-team definitive-award announcement in February 2024. No separately priced bridge marine award identified.
Execution window
Contractor August 2026 bulletin announces September-October foundation/bank sequence and a later September cable-crossing window; these are planned dates, not accepted work or a commissioning deadline.
Works package
Replacement movable bridge basement, in-water central support foundations, navigation protection, bank sheet piles and underwater power/data crossing. Other N206 bridges and road elements remain distinct.
Marine interfaces
Weekday passage restrictions and a separate continuous cable-crossing closure interact with in-water workfront access. Longer possible working hours do not themselves alter navigation closure hours. The schematic is not a navigation notice.
Commercial evidence boundary
The operating connection and foundations require different access interfaces within a wider transport package. A contractor programme does not establish a new marine contract, subcontract allocation, selected vessel fleet or completed installation.

Contract and delivery chain

Work packages and named roles

Published scope, named parties and supporting evidence for each workstream.

Bridge foundations

Basement, central support and bank works

Named party
Boskalis Nederland
Evidence status
Confirmed
Source position
Contractor reports August concrete placement and schedules separate in-water workfronts; quantities and acceptance not confirmed. Source
Operating connection

Underwater power/data crossing

Named party
Boskalis Nederland
Evidence status
Confirmed
Source position
Dedicated later-September window announced, not confirmed installed or tested. Source

Evidence gap

What remains unverified

Outstanding evidence

  • Reported installation and testing for the control connection
  • Final bridge permission and acceptance records
  • Dated navigation arrangements for separate workfronts
  • Foundation quantities and identified marine equipment

Reporting status

Project phase
Construction
Evidence confidence
Confirmed
Last checked
5 September 2026
Cited sources
4

Sources and related records

Project changes Methodology Email a correction Project tracker