Project record

Aqaba oil and chemical pipeline crossings

Participation
Requires review
Participation checked

16 November bids; document collection ended

Participation source

ADC is procuring a pipeline bridge and crossing culverts near the oil bridge. Existing oil and chemical services, foundation excavation and drainage protection form a common construction workfront.

Aqaba oil and chemical pipeline crossings project diagram: 89/A/2026 / civil crossing package; JOD 40,000 security /180 days; Bids before noon Jordan /16 November.

IMWO original project diagram; source: Aqaba Development Corporation

Location

Jordan / Middle East

Segment

Pipeline bridge and hydraulic culverts

Phase

Tender / Confirmed

Last checked

1 November 2026

Coverage

Related sectors

Pipeline bridge and hydraulic culverts is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Aqaba Development Corporation
Procurement references
89/A/2026
Delivery parties
Civil contractor selection under 89/A/2026; qualifying Jordanian contractor classifications stated in the invitation.
Contract route
Procurement reference 89/A/2026. Owner invitation for pipeline crossing civil works with a JOD 40,000 guarantee valid 180 days; document collection ended 27 October 2026.
Execution window
Queries by 1 November 2026 and bid delivery before noon Jordan time on 16 November 2026. A construction start or contract completion date is not supplied in the invitation.
Works package
Surveys, geotechnical work, reinforced-concrete foundations and piers, retaining structures, steel pipe racks, crossing culverts, existing-pipeline protection and drainage.
Marine interfaces
The south-Aqaba workfront lies near the oil bridge. Existing pipeline geometry and service-owner requirements constrain excavation, temporary support and the installation of new structures.
Commercial evidence boundary
The published document-collection period has ended. Existing participants face a near-term query cutoff; entry after that date depends on ADC instructions and permitted access to the issued documents.

Evidence gap

What remains unverified

Outstanding evidence

  • ADC clarifications and access after the document-collection cutoff
  • Verified existing services and temporary protection sequence
  • Drainage levels, foundations and pipe-rack installation interfaces

Reporting status

Project phase
Tender
Evidence confidence
Confirmed
Last checked
1 November 2026
Cited sources
4