Project record

Port Ellen ferry terminal marine redevelopment

Participation
Awarded
Participation checked

Marine construction programme; owner 9 October steel-pile import and local-transfer plan, with actual receipts to confirm.

Participation source

CMAL's Port Ellen terminal redevelopment combines dredging, reclamation and new ferry infrastructure. Its 9 October logistics plan schedules steel-pile imports by vessel, followed by lorry transfer from the pier to storage beside Islay Airport. McLaughlin & Harvey holds the wider construction appointment.

Port Ellen pile logistics records: pier discharge and condition, compound bundle receipts and storage, and inspected pile release to the workfront

IMWO original Port Ellen material-logistics record diagram based on the CMAL steel-pile plan

Location

United Kingdom / Europe

Segment

Marine infrastructure

Phase

Construction / Confirmed

Last checked

28 October 2026

Coverage

Related sectors

Marine infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Caledonian Maritime Assets Limited (CMAL)
Delivery parties
McLaughlin & Harvey
Contract route
Owner March 2026 announcement appoints McLaughlin & Harvey to the wider terminal construction package. No independent dredging award value or subcontract allocation established.
Execution window
The 9 October plan expected imports in the week beginning 12 October, weather permitting, and three to four days of local road transport. The September notice described an earlier anticipated two-week Phase 3 dredging period.
Works package
Capital dredging, reclamation and ferry berthing infrastructure, with linkspan, ramp, shore power and terminal facilities in the wider development. Marine and landside scopes are not separately priced here.
Marine interfaces
Buoyed inner-harbour access, barge-master coordination, separate berth restrictions, dredging records and post-completion surveys connect marine works to existing harbour use. This record is not navigational advice.
Commercial evidence boundary
Sea delivery limits the island-wide road leg while adding pier unloading, storage and subsequent workfront handling. A logistics allowance needs pile bundle weights, trailer and lifting availability, compound capacity and dated receipts alongside the agreed operating windows.

Contract and delivery chain

Work packages and named roles

Published scope, named parties and supporting evidence for each workstream.

Capital dredging

Phased dredging and verification interface

Named party
CMAL
Evidence status
Confirmed
Source position
September 4 owner notice reports Phase 3 begun, with an anticipated next phase; accepted quantities and depth are not established. Source
Terminal construction

Wider marine and ferry infrastructure

Named party
McLaughlin & Harvey
Evidence status
Confirmed
Source position
March owner announcement identifies the main construction appointment, not a separate dredging subcontract or price. Source

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

Owner schedules steel-pile vessel delivery

CMAL plans sea imports followed by three to four days of lorry transfers from the pier to airport-adjacent compounds, subject to weather and operational conditions.

Source

Phase 3 dredging reported underway

The dated owner notice reports a phased dredging workfront with anticipated transition after about two weeks and managed inner-harbour access.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Dated vessel discharge and compound receipt records
  • Pile handling weights, storage condition and workfront release
  • Current harbour notices and road-movement windows
  • Operative marine permissions and project-specific survey acceptance

Reporting status

Project phase
Construction
Evidence confidence
Confirmed
Last checked
28 October 2026
Cited sources
7

Sources and related records

Project changes Methodology Email a correction Project tracker

Project sources 7