Port Ellen pile logistics connect vessel delivery to island roads

Published 28 October 2026 Publisher IMWO Region Europe Confidence Confirmed
Port Ellen pile diagram: vessel discharge, local lorry haul and airport-adjacent storage

IMWO original piles engineering diagram from the cited primary records

Port Ellen's pile-material plan connects vessel discharge to lorry transfers and storage beside Islay Airport. The arrangement requires handling capacity at the pier, compound and eventual construction workfront.

The owner planned a weather-dependent unloading and transfer period

The 9 October notice scheduled imports for the week beginning 12 October, weather permitting, and anticipated three to four days of road movements during normal working hours. It states alignment with local-authority approval. CMAL's 26 October NTM 32/26 separately reports an isolated-danger marker in Kilnaughton Bay displaced to the northeast and advises caution until restoration. The current warning is an arrival-planning input; the 9 October account remains a planned material movement.

Storage separates the ship call from the piling demand

Landing into a compound allows a vessel delivery to be handled on a different timetable from installation. The arrangement also creates two handling interfaces: pier to storage, and storage to the eventual workfront. A supply schedule needs the delivered pile lengths, bundles and handling weights alongside trailer availability and compound lifting capacity. A slow pier-to-compound transfer can occupy the unloading area even when the sea passage has been completed.

Evidence conclusion

Delivery evidence should follow each handling stage

The main contractor's short-term programme can connect the vessel call to unloading records, compound receipts, inspected material condition and releases to the workfront. That provides a firmer basis for booking lifting plant and road movements than the original weather-dependent delivery week. Harbour arrival arrangements should incorporate the active notices and Harbour Master instructions at the time of the call.

Outstanding evidence

  • Dated vessel discharge and compound receipt records
  • Pile handling weights, storage condition and workfront release
  • Current harbour notices and agreed road-movement windows