Location
Lesotho / Africa
Project record
Lesotho's Lowlands Water Development Project Phase II package W03A combines a Hlotse River intake at Ha Setene, raw-water pumping, a 25 million litre-per-day treatment plant, treated-water conveyance, command reservoirs and associated pumping. World Bank contract data names China International Water & Electric Corp. as the USD 42,553,432.19 design-build contractor and Zutari Lesotho as the separate USD 1,013,964.54 construction-supervision consultant. No controlled public source identifies a lower-tier subcontractor.
Lesotho / Africa
Water intake and treatment works
The official LLWDP dashboard currently displays 85% overall progress under a malformed update date; the last fully dated World Bank restructuring paper recorded 65% physical completion after a 24 February 2026 flood compromised the temporary river diversion and cofferdam, delaying intake works / Confirmed
3 August 2026
Coverage
Water intake and treatment works is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe LLWDP site currently displays W03A at 85% overall progress, but the update date omits the month and the same page shows a 23% water-treatment subtask; construction status remains until a dated update reconciles both figures.
SourceThe World Bank restructuring paper records no injury after the work stoppage but says the event delayed the critical intake works and required redesign, rebuilding, drainage and cleaning before the intake-to-commissioning sequence could resume.
SourceThe LLWDP/C/03(A) award identifies Zutari as the independent construction-supervision consultant engaged separately from CWE's design-build works contract; it does not identify a CWE subcontractor.
SourceThe LLWDP/W/03(A) award names China International Water & Electric Corp. as the USD 42.553 million contractor for the intake, pumping, treatment, reservoir and transmission package.
SourceEvidence gap