Mexico has restarted procurement for the first 2,200 l/s module of the Rosarito desalination plant. The current Compras MX detail lists invitation procedure IO-16-B00-016B00985-I-148-2026 as vigente, with proposal opening deferred to 24 July at 11:00 and the ruling scheduled for 29 July at 17:00. A September 2025 federal-state agreement includes seawater intake, brine discharge, conveyance, storage, connections and electrical works in the wider project, while the current procedure description names the plant and pumping plant only.
Project signal
Tender in Mexico
Current statusCompras MX lists the invitation as current, with proposal opening deferred to 24 July 2026 and the ruling moved to 29 July; no award is publishedSource confidenceConfirmed
Location
Mexico / Americas
Segment
Marine utilities
Status
Compras MX lists the invitation as current, with proposal opening deferred to 24 July 2026 and the ruling moved to 29 July; no award is published / Confirmed
Last checked
18 July 2026
Coverage
Related sectors
Marine utilities is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
Comision Nacional del Agua and the Government of Baja California
Delivery parties
No construction or marine works contractor selected; Compras MX lists the invitation as vigente
Contract route
Compras MX lists international open invitation-to-at-least-three-persons procedure IO-16-B00-016B00985-I-148-2026 under internal reference LPIA-AN-019-2026. The legal basis is the exception available after a public tender is declared void without changing its requirements. The current record gives a 10 July site visit, 13 July clarification meeting, proposal opening on 24 July at 11:00 and ruling on 29 July at 17:00. It also carries an annex titled as a notice deferring the proposal-opening date and time. No invited firms, award or contractor are published in the reviewed detail.
Execution window
Compras MX gives 31 July 2026 as the estimated contract start, 1 August as the estimated physical start and 1,096 calendar days across four fiscal years. These are tender-stage dates, not achieved milestones. The procedure remained vigente when reviewed on 18 July 2026.
Works package
The current CONAGUA summary describes construction of the Rosarito desalination plant and a pumping plant serving Tijuana and Playas de Rosarito. The September 2025 coordination agreement defines the wider first-module project as the plant, intake works, brine discharge, a conveyance line, the Rosarito tank, intake and discharge connections, electrification and electromechanical works. The reviewed invitation summary does not show whether all of those components are included in one contract.
Marine interfaces
The 2025 agreement expressly includes intake works, brine discharge and their connections. The 2024 environmental file describes a larger 4,400 l/s site using idle cooling-water intake boxes and the discharge canal at the CFE Presidente Juarez power station. That environmental envelope supports the coastal route, but it does not prove that the entire 4,400 l/s arrangement or a separate offshore package belongs to the current 2,200 l/s invitation.
Commercial evidence boundary
Rosarito is a live desalination construction opportunity with a confirmed marine interface, but the public detail is still not enough to price or qualify the coastal scope. Compras MX sets a 50:50 technical-economic points split, a 30% advance, a 10% performance guarantee and separate liability and environmental insurance each at 10%. Those are tender terms, not a contract award or final allocation to the intake and discharge works. The proposal opening, ruling, invited firms and signed package boundary remain unpublished.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
The live procedure detail moved proposal opening from the earlier 21 July programme date to 24 July at 11:00 and lists the ruling for 29 July at 17:00. An annex is identified as the notice deferring the proposal-opening date and time.
The project returned to procurement after the previous public tender was declared void. The new register schedules proposals for 21 July and a ruling for 24 July.
Federal-state coordination agreement was published
The agreement fixed the current first module at 2,200 l/s and listed the plant, intake, brine discharge, conveyance, storage, connections and electrical works as project components.
The filing described a 4,400 l/s full-site envelope using existing CFE cooling-water intake boxes and the power station's discharge canal for brine return.