Four IFC advisory procurements define transaction preparation; the 100 MLD PPP, marine site, concession and works remain unawarded
IDCO and IFC are preparing a proposed 100 MLD seawater desalination PPP for Gopalpur Industrial Park in Odisha. The project is still upstream: demand, tariffs, phasing and site selection must be reconciled before the seawater intake, brine outfall, shore crossing and raw-water transfer system can be fixed. Odisha's PPP register lists the scheme at INR 500 crore and Proposed; no concessionaire, EPC contractor, final site or marine permit is public.
India / Asia Pacific
Marine utilities
Planning / Confirmed
18 July 2026
Coverage
Marine utilities is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe state database identifies the Industries Department project and an INR 500 crore planning cost. It does not establish budget approval, final capacity, a concession tender, award or construction start.
SourceThe two briefs put site investigations, intake and outfall concepts, demand commitments, tariffs, phasing, financial modelling and bankability into the same transaction-preparation sequence. Their 20 July EOI deadline is for advisers, not for a concessionaire or works contractor.
SourceThe brief explicitly places the marine intake and outfall in the Coastal Regulation Zone and requires review of marine ecology, brine effects, fishing and coastal livelihoods, tourism, public access and climate risk.
SourceThe legal brief covers regulatory due diligence, PPP structure, risk allocation, approvals, transaction documents and bid support for a phased 100 MLD plant and associated intake, outfall and transmission system.
SourceThe river-intake notification is evidence of a separate or alternative industrial-water route for Gopalpur Industrial Park. It must not be merged into the seawater PPP or treated as its intake design.
SourceEvidence gap