Project record
Western Australia's Alkimos plant combines a 2.5 km seawater-intake tunnel, a 4 km brine-outfall tunnel, two offshore intake structures, four vertical risers, and a 130 m diffuser with the first 50 billion litres per year of desalination capacity. By July 2026 the intake tunnel and all offshore piling were complete, while the outfall tunnel and diffuser connection remained active.
Australia / Asia Pacific
Marine utilities
Intake tunnel and offshore piling complete; outfall tunnel and diffuser installation remained active after the original June 2026 marine-work window / Confirmed
15 July 2026
Controlled taxonomy
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Material change register
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
Water Corporation's July panel records all intake and outfall piling complete and the final outfall-diffuser installation phase under way. This advances the offshore package but also shows that the annual report's June 2026 marine-construction endpoint was not an acceptance date; diffuser placement, connection, testing and marine demobilisation remained open.
Read controlling sourceThe owner's June panel records TBM Mary completing the 2.5 km intake drive in 196 days, all offshore piling complete and TBM Karli about 80% through the 4 km outfall drive. Intake-tunnel completion does not prove permanent riser connection, outfall completion, accepted diffuser performance, integrated testing or first water.
Read controlling sourceThe Western Australian Government recorded arrival of the 78 m-leg jack-up barge with a 400 t crane for 24-hour installation of ocean intake and outfall structures. Vessel arrival and offshore activity establish mobilisation, not installed or accepted marine assets.
Read controlling sourceTransport WA issued two 500 m-radius closure notices for intake and outfall works beginning on 10 December 2025, identifying Beverley, Pilbara 400 SEMP, support tugs and work barges. A regulated marine work zone proves planned and authorised activity, not completed piling or structural acceptance.
Read controlling sourceWater Corporation announced that two more-than-four-metre-diameter TBMs would begin an 18-month programme beneath the seabed for a 2.5 km intake and 4 km outfall. Assembly and launch readiness do not prove tunnel advance, breakthrough, lining acceptance or offshore connection.
Read controlling sourceThe alliance sustainability report dates construction from August 2024 and separates it from detailed design, tunnelling, marine construction, commissioning and operation. This is a programme phase boundary, not evidence that offshore works or tunnel excavation had started in August.
Read controlling sourceJacobs identified design, build, operation and maintenance scope with Water Corporation and ACCIONA, including separate 2.5 km intake and 4.1 km outfall tunnels. The appointment establishes delivery responsibility but not construction mobilisation or accepted marine output.
Read controlling sourceEPA records Ministerial Statement 1207 approval for the plant and its marine components. Approval allows implementation under conditions; it is not an alliance award, notice to proceed, construction start or operating approval.
Read controlling sourceDelivery watch
Confirm completion and acceptance of the outfall diffuser and 4 km outfall TBM drive, permanent tunnel-to-riser connections, closure of residual marine exclusion zones, then integrated intake, outfall, plant, power, transfer-pipeline, and first-water testing.
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Read featured analysis Review methodology Submit stronger evidence or a correction Open project trackerEPA records environmental approval on 10 August 2023. Jacobs then identified its Water Corporation-ACCIONA alliance appointment on 19 April 2024, and the alliance sustainability report dates the construction phase from August 2024, tunnelling from July 2025, marine construction from November 2025, commissioning from August 2026, and operation from June 2028. Water Corporation's 15 July 2025 release records both TBMs assembled for the 2.5 km intake and 4 km outfall drives. Transport WA issued two closure notices on 9 December 2025 for marine construction beginning on 10 December. The Western Australian Government's 16 March 2026 record confirms Beverley mobilised to install the intake and outfall structures. Water Corporation's June panel records the 2.5 km intake TBM at its destination, the outfall drive about 80% complete, and all offshore piling complete; its July panel says diffuser installation remained the final offshore phase. The monthly panels do not state a day, so their public change dates retain month precision. The two intake structures, 130 m outfall diffuser with 20 ports, vertical risers and bored tunnels form one marine system. Piling, TBM completion, visible offshore structures, exclusion-zone expiry and first water remain separate from permanent connections, testing, owner acceptance, stable output and commercial operation.
Phase: construction. Evidence reviewed: 15 July 2026.