Western Australia's Alkimos plant combines a 2.5 km seawater-intake tunnel, a 4 km brine-outfall tunnel, two offshore intake structures, four vertical risers, and a 130 m diffuser with the first 50 billion litres per year of desalination capacity. By July 2026 the intake tunnel and all offshore piling were complete, while the outfall tunnel and diffuser connection remained active.
Australia / Asia Pacific
Marine utilities
Intake tunnel and offshore piling complete; outfall tunnel and diffuser installation remained active after the original June 2026 marine-work window / Confirmed
15 July 2026
Coverage
Marine utilities is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogWater Corporation's July panel records all intake and outfall piling complete and the final outfall-diffuser installation phase under way. This advances the offshore package but also shows that the annual report's June 2026 marine-construction endpoint was not an acceptance date; diffuser placement, connection, testing and marine demobilisation remained open.
SourceThe owner's June panel records TBM Mary completing the 2.5 km intake drive in 196 days, all offshore piling complete and TBM Karli about 80% through the 4 km outfall drive. Intake-tunnel completion does not prove permanent riser connection, outfall completion, accepted diffuser performance, integrated testing or first water.
SourceThe Western Australian Government recorded arrival of the 78 m-leg jack-up barge with a 400 t crane for 24-hour installation of ocean intake and outfall structures. Vessel arrival and offshore activity establish mobilisation, not installed or accepted marine assets.
SourceTransport WA issued two 500 m-radius closure notices for intake and outfall works beginning on 10 December 2025, identifying Beverley, Pilbara 400 SEMP, support tugs and work barges. A regulated marine work zone proves planned and authorised activity, not completed piling or structural acceptance.
SourceWater Corporation announced that two more-than-four-metre-diameter TBMs would begin an 18-month programme beneath the seabed for a 2.5 km intake and 4 km outfall. Assembly and launch readiness do not prove tunnel advance, breakthrough, lining acceptance or offshore connection.
SourceThe alliance sustainability report dates construction from August 2024 and separates it from detailed design, tunnelling, marine construction, commissioning and operation. This is a programme phase boundary, not evidence that offshore works or tunnel excavation had started in August.
SourceJacobs identified design, build, operation and maintenance scope with Water Corporation and ACCIONA, including separate 2.5 km intake and 4.1 km outfall tunnels. The appointment establishes delivery responsibility but not construction mobilisation or accepted marine output.
SourceEPA records Ministerial Statement 1207 approval for the plant and its marine components. Approval allows implementation under conditions; it is not an alliance award, notice to proceed, construction start or operating approval.
SourceEvidence gap