Alkimos completes intake tunnel as offshore acceptance continues
Alkimos has completed its 2.5 km intake tunnel and all offshore piling, but the 4 km outfall drive and 130 m diffuser remained active after the original June 2026 marine-construction window. Permanent connection and accepted system testing are still needed before the marine interface can be called complete.
What changed
EPA records environmental approval on 10 August 2023, Jacobs identifies the alliance appointment on 19 April 2024, and the alliance sustainability report separates construction from later tunnelling, marine construction, commissioning and operation. Water Corporation's 15 July 2025 release records both TBMs assembled for separate 2.5 km intake and 4 km outfall drives. Transport WA's 9 December notices establish the two offshore work zones from 10 December 2025. The Western Australian Government records Beverley's 16 March 2026 marine mobilisation. Water Corporation's June panel says the intake TBM reached its destination, the outfall drive was about 80% complete and all offshore piling was complete; its July panel still had outfall-diffuser installation active. Those owner panels publish month precision only, so the dates remain at month precision rather than being assigned an unsupported day. The annual schedule's June 2026 marine endpoint and July 2026 tunnelling endpoint were programme points, not acceptance evidence.
Why it matters
A desalination project can appear advanced onshore while its first-water date remains exposed to a small number of offshore connections. Alkimos's annual programme placed marine construction through June 2026, yet the owner's July panel still had diffuser installation active. The two intake structures, 130 m diffuser, four vertical risers, 2.5 km intake tunnel and 4 km outfall tunnel must meet within survey, environmental and mechanical tolerances before integrated testing can begin.
Decision read
What remains open
The offshore campaign is nearing its physical finish, but the owner's July panel shows that the original June marine-construction point was not completion or acceptance. Diffuser installation and the outfall drive still have to meet precisely at the risers before permanent connections and marine-system testing can begin. Marine works can then converge with plant, power and transfer-pipeline commissioning. Finished piling, closed work zones and a complete intake drive do not settle those interfaces.
Next watchpoints
- Completion and survey acceptance of the 130 m outfall diffuser
- Outfall TBM advance, breakthrough, and marine-riser connection after the original July 2026 programme point
- Permanent connections to both offshore intake structures
- Underwater-noise, fauna-observation, water-quality, and seabed controls
- Integrated testing path to first water in 2028
Knowledge context
Related knowledge topics
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Sources used 9
- Alkimos Seawater Desalination Plant project and July 2026 marine work update Water Corporation, Western Australia, July 2026
- Alkimos desalination project milestone securing Western Australia's water future Government of Western Australia, 16 March 2026
- Water that is Made in WA to cater for the State's growing population Water Corporation, Western Australia, 15 July 2025
- Alkimos marine construction navigation closures Transport WA, 9 December 2025
- Alkimos Seawater Desalination Plant Stage 1 annual sustainability report Water Corporation, Western Australia, 2025
- Alkimos marine construction fact sheet Water Corporation, Western Australia, 2025
- Jacobs to support design, construction and operations for seawater desalination plant Jacobs, 19 April 2024
- Alkimos Seawater Desalination Plant project profile ACCIONA, Publication date not stated; evidence reviewed 15 July 2026
- Alkimos Seawater Desalination Plant proposal Environmental Protection Authority of Western Australia, 10 August 2023
Corrections and methodology
Facts are dated to the source record above. IMWO updates the brief when procurement, award, delivery, or scope evidence materially changes.
Review methodology Open intelligence archive Submit a correction