Location
Solomon Islands / Global islands
Project record
Honiara has rehabilitated two old wastewater outfalls and built part of the eastern sewer network, but the next marine package is not settled in public. The 2023 EIA designs two lines: 350 m by 400 mm at the National Referral Hospital and 500 m by 800 mm at Ranadi. Solomon Water's 2025 plan also repeats an older three-outfall basis with a 900-1,000 m by 357 mm NRH line and a 500 m by 312 mm Soap line, while separately budgeting NRH and Ranadi packages. ADB still lists bid documents in preparation and no new-outfall works award.
Solomon Islands / Global islands
Marine utilities
ADB still lists bid-document preparation for the new marine works; Solomon Water's public plan carries competing three-outfall, two-new-outfall and NRH/Ranadi package definitions, with no works award disclosed / Confirmed
19 July 2026
Controlled taxonomy
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Material change register
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
The current record confirms two existing-outfall rehabilitations but does not disclose a construction award for the purpose-built NRH and Ranadi marine lines.
Read controlling sourceThe approval supports Honiara sewer reconfiguration, but the EIB environmental sheet limits its project to new sewer lines and a 60 cubic metre-per-day septage plant and says the new pump stations and sea outfalls are not included.
Read controlling sourceADB's current implementation record reports 3.2 km constructed by 30 June 2025. That progress belongs to the landward network and does not establish marine outfall construction.
Read controlling sourceThe assessment defined a 350 m NRH line and 500 m Ranadi line, six pump stations and about 15 km of sewers, while leaving the final offshore installation method to procurement.
Read controlling sourceDelivery watch
Look for issued NRH and Ranadi tenders that fix the number of new outfalls, final geometry, funding and package boundaries, followed by bidder disclosure, award, physical mobilisation and accepted discharge performance.
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Read featured analysis Review methodology Submit stronger evidence or a correction Open project trackerADB currently records two rehabilitated outfalls complete and preparation of bidding documents for the new works still ongoing. The February 2023 EIA defines the later two-line baseline: 350 m by 400 mm at NRH and 500 m by 800 mm at Ranadi. Solomon Water's 2025 plan repeats an older 2019 basis with three outfalls, a 900-1,000 m by 357 mm NRH line and a 500 m by 312 mm Soap line, then separately carries USD 13.2 million for NRH and USD 23.8 million for Ranadi with a Q2 2027 planning date. ADB's August 2022 Goodwood land plan records another interim design state: a replacement short beach outfall at Goodwood, with long-term consolidation to a single Soap outfall. It is design-history evidence, not authorization for the later NRH and Ranadi deep-sea pair. The planning figures and dates are not awards. EIB's related facility excludes the new pumping stations and sea outfalls. The October 2024 field account and 2025 safeguards report document the separate landward sewer works.
Phase: tender. Evidence reviewed: 19 July 2026.