Project record

Fujairah I IWP seawater intake and outfall

Lantania project rendering of the planned Fujairah I reverse-osmosis plant, two domed water-storage tanks and adjacent port waterfront

Lantania; exact Fujairah I project rendering, not a construction image

EtihadWE's development and investment arm signed the AED 1.046 billion EPC agreement for Fujairah I with NMDC Infra and Lantania Aguas on 7 May 2026. The 60 MIGD plant at the Port of Fujairah includes a submarine intake tower, two GRP intake pipelines, intake pumps and a GRP marine outfall sized for the full seawater abstraction volume. The award defines a substantial marine package; a notice to proceed, offshore mobilisation and installed quantities are not published.

Project signal

Award in UAE

Treat Fujairah I as an awarded desalination EPC with a confirmed marine scope, not as a construction project. The owner fixes the contract, capacity, site and approximate programme; Lantania defines the intake and outfall arrangement and assigns civil and marine works to NMDC. Pipe diameters, lengths, alignments, landfall method, diffuser geometry, construction quantities, marine environmental controls and accepted dates remain unpublished.

Current status EPC agreement signed on 7 May 2026; no notice to proceed or marine mobilisation is published Source confidence Confirmed

Location

UAE / Middle East

Segment

Marine utilities

Status

EPC agreement signed on 7 May 2026; no notice to proceed or marine mobilisation is published / Confirmed

Evidence reviewed

20 July 2026

Controlled taxonomy

Related sectors

The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.

Knowledge context

Related knowledge topics

Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.

Project anatomy

Scope, counterparties, and execution logic

Client / authority
Development and investment arm of Etihad Water and Electricity (EtihadWE)
Delivery parties
NMDC Infra - civil and marine works and installation, Lantania Aguas - engineering, key process equipment, installation supervision and start-up
Contract route
Engineering, procurement and construction agreement between EtihadWE's development and investment arm and the NMDC Infra-Lantania Aguas consortium. EtihadWE describes Fujairah I as its second privately procured IWP after Naqa'a IWP.
Execution window
EtihadWE and Lantania describe an approximately 30-month delivery period covering civil works, process systems and commissioning. Initial operation is expected at partial capacity before full 60 MIGD production. Neither source publishes a notice-to-proceed date, first-water date or accepted commercial-operation date.
Works package
Deliver a 60 MIGD, approximately 272,765 m3/day seawater reverse-osmosis plant on about 10 hectares within the Port of Fujairah. The works include two water-storage tanks providing 18 hours of production, a submarine intake tower, two GRP intake pipelines, redundant intake pumping and a GRP marine outfall for concentrate and treated effluents sized to handle the full seawater abstraction volume.
Marine interfaces
NMDC's civil and marine works must connect the offshore intake tower, twin intake lines, shoreline and intake pumping to Lantania's process system, then return concentrate and treated effluents through the marine outfall. Detailed survey, seabed and geotechnical data, pipe handling and jointing, landfall works, offshore installation, tie-ins, hydraulic testing, discharge performance and port-interface controls have not been published.
Commercial read
The plant EPC is awarded, so the remaining market lies inside consortium procurement rather than a new owner-level EPC competition. Potential specialist demand may include marine survey and geotechnics, GRP supply and jointing, marine plant, landfall and pipeline installation, diving and survey support, environmental monitoring and hydraulic commissioning, but no subcontract awards or procurement packages are public yet.
Next milestone
A dated notice to proceed or mobilisation record, followed by approved marine design geometry, named specialist packages, intake-tower and pipeline installation evidence, hydraulic testing, partial first water and owner acceptance at 60 MIGD.

Material change register

What changed, when, and what it proves

Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.

EtihadWE signed the AED 1.046 billion EPC agreement

The owner confirmed NMDC Infra and Lantania Aguas as the EPC consortium for a 60 MIGD plant and described an approximately 30-month delivery programme. Contract signature establishes delivery responsibility, not notice to proceed, marine mobilisation or construction progress.

Read controlling source

Lantania defined the intake-outfall scope and NMDC marine role

The contractor record identifies a submarine intake tower, two GRP intake pipelines, a GRP marine outfall and NMDC responsibility for civil and marine works. It does not publish final geometry, installation method, subcontract awards or accepted quantities.

Read controlling source

Delivery watch

Evidence needed next

A dated notice to proceed or mobilisation record, followed by approved marine design geometry, named specialist packages, intake-tower and pipeline installation evidence, hydraulic testing, partial first water and owner acceptance at 60 MIGD.

Decision watchpoints

  • Notice to proceed, detailed-design release and confirmed construction start
  • Intake and outfall diameters, lengths, alignments and shore-crossing method
  • Submarine intake-tower, marine outfall and any diffuser geometry
  • Named marine subcontractors, GRP suppliers and installation plant
  • Bathymetric, geotechnical, environmental and port-interface controls
  • Installed quantities, as-built surveys, tie-ins and hydraulic testing
  • Partial-capacity first water kept separate from full 60 MIGD acceptance

Project availability status

This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.

Read featured analysis Review methodology Submit stronger evidence or a correction Open project tracker

Record control

Evidence reviewed date is not a project-event date.

IMWO changes phase, participants, scope, completion, or acceptance wording only when a dated source establishes the change. The review date records when the evidence set was checked; it does not claim that physical work changed on that date.

Evidence reviewed 20 July 2026 Sources in this record 4

Source record

EtihadWE's 7 May release fixes the EPC signature, AED 1.046 billion total investment, 60 MIGD contracted capacity, Port of Fujairah site, 18-hour storage and approximate 30-month programme. Lantania's 6 May release and current project page define the submarine intake tower, twin GRP intake pipelines, GRP marine outfall and the allocation of civil and marine works to NMDC. NMDC's own 6 May release confirms the EPC agreement and total project value. A notice to proceed, pipe diameters and lengths, diffuser arrangement, construction quantities, installation method, approved marine controls, first water and commercial acceptance are not published.

Phase: award. Evidence reviewed: 20 July 2026.

Project sources 4