The Casablanca-Settat PPP is building 300 million m3/year of seawater reverse-osmosis capacity at Sidi Rahal in two phases. ONEE's owner-issued prequalification basis requires the first phase to deliver marine intake and discharge works sized for the final 822,000 m3/day plant, alongside the common tunnelling and electrical systems.
Morocco / Africa
Marine utilities
Construction active; common marine, tunnelling, and electrical systems remain on the path to the February 2027 first-phase target / Confirmed
10 August 2026
Coverage
Marine utilities is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogACCIONA's Q1 statement says Water revenue growth and backlog execution were driven in part by construction at Casablanca. It confirms active contractor delivery through 31 March 2026 but does not identify completed marine structures, tunnel advance, wet testing, or owner acceptance.
SourceACCIONA's 2025 integrated report attributes part of Water's improved performance to faster-than-expected delivery of key projects including Casablanca. This is a current execution signal, not a measured marine-progress percentage, tunnel breakthrough, common-system acceptance, first water, or operating release.
SourceThe owner describes Casablanca as in progress at the end of 2025 and retains the 300 million m3/year, clean-energy programme frame. This confirms owner-side construction status but provides no marine-package quantity, completion measure, acceptance certificate, or first-water evidence.
SourceACCIONA identified the 50/45/5 consortium split, 80/20 debt-equity structure, MAD 6.5 billion investment, renewable-power supply and 27-year construction and O&M role. Financing removes a commercial gate; it does not prove marine mobilisation, physical progress or accepted output.
SourceThe owner marked the start of project realization and set the two-phase capacity and programme. Construction launch moves the project into execution while marine method, tunnel progress, permanent intake and discharge installation, integrated testing and operation still require dated confirmation.
SourceONEE records the PPP conclusion in November 2023 for design, finance, construction and more than 27 years of operation. The agreement establishes responsibility and delivery structure, not notice to proceed, construction start or marine-system definition and acceptance.
SourceDossier 01DAM/EE/2022 requires the first phase to deliver intake and discharge works sized for 822,000 m3/day, including intake towers, emissaries, basin civil works, screening and desanding, discharge dilution and controls; it is an owner procurement basis, not evidence of final geometry, completion or acceptance.
SourceEvidence gap