Marine Utilities

Casablanca makes common marine works the first-phase schedule test

Published 13 July 2026 Updated 15 July 2026 Editorial responsibility IMWO Region Africa Confidence Confirmed
Casablanca desalination deputy project director Meryem Hadri at the active ACCIONA construction site

ACCIONA People

Casablanca's first 200 million m3/year stage is carrying the marine works, tunnelling and electrical systems shared by the eventual 300 million m3/year plant. The February 2027 first-phase target therefore depends on acceptance of those common systems, not visible onshore progress alone.

What changed

ONEE records the November 2023 PPP, construction commencement on 10 June 2024 and the two-stage delivery structure, and its year-end 2025 profile keeps the plant under construction. ACCIONA's financing release identifies the MAD 6.5 billion PPP, the Al Baidaa Desalination Company ownership split, 300 million m3/year of final production, and a 27-year construction and O&M role. Its Q1 2026 statement and June 2026 integrated report confirm continued contractor execution but do not quantify marine progress. A current project-team profile states that the first phase includes common marine works, tunnelling, and electrical systems, with first-phase completion targeted for February 2027 and second-phase completion for August 2028. ACCIONA's project profile gives 559,000 m3/day in the first stage and 279,500 m3/day in the second. NOVEC's marine study confirms that bathymetry, geology, seawater quality, waves, and currents form part of the technical basis. Moroccan project reporting identifies two approximately 1.85 km seawater-intake lines and an approximately 2.5 km discharge outfall. Completed tunnels, accepted intake-outfall systems, first water and commercial operation have not been confirmed.

Why it matters

Shared intake, discharge, tunnel, and electrical assets concentrate schedule risk: a late or partially accepted interface can hold back both the first operating block and the later 100 million m3/year expansion. Suppliers and project watchers should therefore follow tunnel and shaft completion, intake-outfall integration, energisation, testing, and owner acceptance as one sequence.

Decision read

What remains open

Casablanca concentrates both phases' schedule risk in the common marine, tunnel and electrical systems. First-stage acceptance must support initial production and the later expansion. The sequence runs from tunnel and shaft completion through permanent intake and discharge connections, energisation and wet testing, then accepted first-phase output and commercial operation. Construction revenue or a target date alone does not establish that progression.

Next watchpoints

  • Physical completion of common marine and tunnelling systems
  • Permanent intake and discharge connections and wet testing
  • Electrical energisation and first-phase integrated commissioning
  • ONEE confirmation of first water and operating acceptance
  • Interface readiness for the additional 100 million m3/year stage

Knowledge context

Related knowledge topics

Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.

Sources used 9

Corrections and methodology

Facts are dated to the source record above. IMWO updates the brief when procurement, award, delivery, or scope evidence materially changes.

Review methodology Open intelligence archive Submit a correction