Project record

Rabigh 4 IWP intake, outfall and storage system

Rawabi Water Desalination Company entrance and storage buildings at the Rabigh 4 IWP site

ACWA Power; exact Rabigh 4 IWP project image

SEPCOIII reports that Rabigh 4 completed its EPC performance test on 19 February 2026 at the plant's 600,000 m3/day design capacity. The disclosed test power use was 2.712 kWh/m3, or 2.659 kWh/m3 after photovoltaic generation. Modern Marine's project record identifies a 1,500,000 m3/day seawater intake and a 900,000 m3/day outfall, making the marine system a defined part of the delivery chain rather than an assumed coastal interface.

Project signal

Commissioning in Saudi Arabia

The performance test is a late commissioning milestone, not a substitute for the project company's commercial-operation certificate, SWPC acceptance, final intake-outfall handover or sustained marine environmental performance. Keep the record at commissioning until those separate steps are published.

Current status EPC performance test completed on 19 February 2026; SWPC commercial-operation confirmation remains unpublished Source confidence Confirmed

Location

Saudi Arabia / Middle East

Segment

Marine utilities

Status

EPC performance test completed on 19 February 2026; SWPC commercial-operation confirmation remains unpublished / Confirmed

Evidence reviewed

20 July 2026

Controlled taxonomy

Related sectors

The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.

Knowledge context

Related knowledge topics

Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.

Project anatomy

Scope, counterparties, and execution logic

Client / authority
Saudi Water Partnership Company (SWPC)
Delivery parties
Rawabi Water Desalination Company (project company), ACWA Power, Haji Abdullah Alireza & Co. and Al Moayyed Contracting Group (shareholders), ACCIONA Agua and SEPCOIII (EPC consortium), Modern Marine (marine works contractor)
Contract route
Build-own-operate independent water project under a 25-year water purchase agreement. ACWA reports a USD 675 million investment cost and ownership shares of 45% ACWA Power, 35% Haji Abdullah Alireza & Co. and 20% Al Moayyed Contracting Group.
Execution window
SWPC named the preferred bidder on 26 February 2023 and signed the project agreements on 12 April 2023. ACWA records financial close in September 2023 and scheduled Q1 2026 commissioning. SEPCOIII then reported completion of the EPC performance test on 19 February 2026. SWPC has not published a commercial-operation notice after that test.
Works package
A 600,000 m3/day seawater reverse-osmosis plant, 1,200,000 m3 of potable-water storage, electrical connection works and a 6.804 MWp photovoltaic system. The project-specific marine record gives a 1,500,000 m3/day intake flow and a 900,000 m3/day outfall flow.
Marine interfaces
The plant depends on a high-volume Red Sea abstraction and brine-return system. The evidenced interface runs from offshore intake through shoreline and treatment hydraulics to the outfall, while final as-built geometry, diffuser details, marine acceptance and operating environmental results remain unpublished.
Commercial read
The greenfield EPC package has reached performance testing, so immediate value is more likely to sit in commissioning support, marine inspection, condition baselining, intake and diffuser maintenance, environmental monitoring and operating optimisation than in a new construction tender.
Next milestone
Owner or offtaker confirmation of commercial operation, followed by published intake-outfall handover evidence, sustained output and energy data, and marine environmental performance under normal operation.

Material change register

What changed, when, and what it proves

Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.

The EPC consortium completed the performance test

SEPCOIII reported full design-capacity testing and measured power consumption. The notice does not establish SWPC commercial acceptance, final marine handover or sustained operating performance.

Read controlling source

SWPC named the preferred bidder

The preferred-bidder notice confirmed the 600,000 m3/day plant and 1,200,000 m3 storage scope. It was a procurement milestone, not a construction or operating result.

Read controlling source

Delivery watch

Evidence needed next

Owner or offtaker confirmation of commercial operation, followed by published intake-outfall handover evidence, sustained output and energy data, and marine environmental performance under normal operation.

Decision watchpoints

  • Commercial-operation certificate or owner acceptance from SWPC or the project company
  • Final intake and outfall completion, testing and marine handover
  • As-built intake and outfall alignments, lengths, materials and diffuser configuration
  • Brine-dispersion and receiving-water monitoring under sustained operation
  • Acceptance and operating availability of the 1,200,000 m3 storage system
  • Sustained plant output and power consumption after the EPC test period

Project availability status

This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.

Read featured analysis Review methodology Submit stronger evidence or a correction Open project tracker

Record control

Evidence reviewed date is not a project-event date.

IMWO changes phase, participants, scope, completion, or acceptance wording only when a dated source establishes the change. The review date records when the evidence set was checked; it does not claim that physical work changed on that date.

Evidence reviewed 20 July 2026 Sources in this record 6

Source record

ACWA defines the plant capacity, storage, project company, shareholding, EPC parties, 25-year WPA, investment cost, photovoltaic capacity and scheduled Q1 2026 commissioning. SEPCOIII's dated notice controls the EPC performance-test milestone and the reported power-use figures. SWPC records the preferred-bidder stage, storage scope and later construction classification. Modern Marine supplies the project-specific intake and outfall flow rates and identifies its marine role. SEPCOIII's test notice does not state SWPC commercial acceptance, and the project parties have not published final marine as-built or environmental acceptance records.

Phase: commissioning. Evidence reviewed: 20 July 2026.

Project sources 6