Sharakat, the Saudi Water Partnership Company, has grouped Ras Al Khair 2, Ras Al Khair 3, Tabuk 1, Shuqaiq 4 and Jazan 1 into one developer qualification programme. Their listed capacities add to 2.1 million cubic metres per day. The shared request for qualification makes each future project company responsible for a greenfield seawater reverse-osmosis plant, seawater intake and outfall facilities and related infrastructure. It does not publish the five individual RFPs, marine alignments, environmental approvals, awards or construction programmes.
Project signal
Prequalification in Saudi Arabia
Read the 2.1 million-cubic-metre-per-day total as a development pipeline, not awarded or operating capacity. The shared qualification route identifies recurring intake and outfall responsibilities, but each site's marine scope must be rebuilt from its own RFP, surveys, permits and contract evidence when those records appear.
Current statusSharakat is qualifying developers across five planned seawater reverse-osmosis projects; no individual RFP, award or project-specific marine package is publicSource confidenceConfirmed
Location
Saudi Arabia / Middle East
Segment
Marine utilities
Status
Sharakat is qualifying developers across five planned seawater reverse-osmosis projects; no individual RFP, award or project-specific marine package is public / Confirmed
Evidence reviewed
18 July 2026
Controlled taxonomy
Related sectors
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Related knowledge topics
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Scope, counterparties, and execution logic
Client / authority
Sharakat (Saudi Water Partnership Company)
Delivery parties
No project company, EPC contractor or marine works contractor selected
Contract route
Sharakat is using one request for qualification to screen developers for five future independent water projects. The reviewed programme material does not establish that an individual RFP has been issued for any of the five projects, nor does it identify a preferred bidder, award or executed water-purchase agreement.
Execution window
The current qualification table gives 2026 as the expected launch year for all five projects. It does not provide separate RFP dates, award dates, financial-close deadlines, construction starts or operating dates, so those milestones remain open for each project.
Works package
The programme lists Ras Al Khair 2 at 600,000 cubic metres per day; Ras Al Khair 3, Tabuk 1 and Shuqaiq 4 at 400,000 cubic metres per day each; and Jazan 1 at 300,000 cubic metres per day. The shared RFQ describes greenfield SWRO plants with screening and pumping, pretreatment, reverse osmosis and energy recovery, post-treatment and export, wastewater systems, storage and the seawater intake and outfall facilities required by each eventual RFP.
Marine interfaces
The marine signal is real but still generic. The shared RFQ places seawater intake and outfall facilities with the future project companies and anticipates brine and treated-wastewater discharge. It does not provide site-specific routes, lengths, diameters, materials, diffuser geometry, shore-crossing method, dredging quantities, marine surveys or permit conditions for any of the five plants.
Commercial read
The five published design capacities sum to 2.1 million cubic metres per day. That is a planning total across a qualification pipeline, not contracted capacity, a portfolio under construction or water available to the offtaker. One qualification exercise may create a common bidder pool, but it does not merge the five projects into one physical package or one award.
Next milestone
An individual project RFP or qualification result that fixes the site, procurement timetable and information package for at least one of the five plants, followed by project-specific environmental, survey and marine-design evidence.
Material change register
What changed, when, and what it proves
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
Current portfolio confirms the five-project capacity list
Sharakat's current portfolio lists Ras Al Khair 2, Ras Al Khair 3, Tabuk 1, Shuqaiq 4 and Jazan 1 at a combined planned capacity of 2.1 million cubic metres per day. The list does not establish individual RFPs, bidders, awards or construction starts.
Shared RFQ assigns intake and outfall responsibility
The common qualification document places seawater intake and outfall facilities within each future project company's responsibility. It does not publish the five site-specific alignments, dimensions, permits, marine packages or delivery programmes.
An individual project RFP or qualification result that fixes the site, procurement timetable and information package for at least one of the five plants, followed by project-specific environmental, survey and marine-design evidence.
Decision watchpoints
Separate RFP release for Ras Al Khair 2, Ras Al Khair 3, Tabuk 1, Shuqaiq 4 and Jazan 1
Qualified developers, bidder lists and project-company structures
Site-specific capacity, schedule, water-purchase agreement and risk allocation
Bathymetry, oceanography, geotechnical and seawater-quality investigations
Intake route, screens, pumping, shore crossing and hydraulic design
Outfall route, diffuser, brine dispersion and wastewater handling
Environmental and social impact assessment, marine permits and fisheries conditions
Project award, financial close, EPC packaging and marine contractor selection
Offshore mobilisation, installed works, testing, first water and accepted output
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Evidence reviewed date is not a project-event date.
IMWO changes phase, participants, scope, completion, or acceptance wording only when a dated source establishes the change. The review date records when the evidence set was checked; it does not claim that physical work changed on that date.
Evidence reviewed18 July 2026Sources in this record8
Source record
The current SWPC qualification initiative and RFQ control the five-project list, capacities, expected 2026 launch references and shared project-company responsibilities. Sharakat's current portfolio and individual project pages confirm the same named pipeline. Treat the 2.1 million-cubic-metre-per-day sum as planned design capacity. The common intake and outfall language is a future responsibility, not evidence of accepted routes, permits, awards, mobilisation, installed assets, first water or operating performance.
Phase: prequalification. Evidence reviewed: 18 July 2026.