Project record
Hassyan's first 60 MIGD block is operating and the remaining 120 MIGD is moving through the 2026 delivery window. The confirmed marine scope covers seawater intake and outfall pipelines, diffuser integration beside the adjacent power plant, and capacity provision for a planned additional 60 MIGD.
UAE / Middle East
Marine utilities
Block A commissioned; remaining Phase 1 capacity in delivery / Confirmed
13 July 2026
Controlled taxonomy
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Material change register
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
The first 60 MIGD block entered the installed water-capacity record, moving the project into phased commissioning while the remaining 120 MIGD, full marine-system acceptance, and sustained performance remain separate conclusions.
Read controlling sourceThe progress report narrowed the delivery window and put construction at an advanced stage. A percentage-complete statement left first water, accepted output, intake-outfall performance and commercial operation unverified.
Read controlling sourceThe owner announcement set the financed 30-year IWP delivery structure and committed development route. It contained no marine construction progress, commissioning result or accepted desalination capacity.
Read controlling sourceDelivery watch
Verify commissioning of the remaining two 60 MIGD blocks, final intake-outfall acceptance, marine water-quality performance, and the trigger for the planned 60 MIGD expansion.
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Read featured analysis Review methodology Submit stronger evidence or a correction Open project trackerDubai Electricity and Water Authority reporting says the 180 MIGD Hassyan seawater reverse-osmosis independent water project was about 90% complete in January 2026 and that all phases were scheduled for completion in the first quarter of 2027. DEWA's Q1 2026 results, published in May, confirm that the first 60 MIGD block had entered service and that a further 120 MIGD was expected during 2026. ACWA Power's project page identifies the 30-year BOO structure, Hassyan Water Company A, SIDEM and SEPCO III as the EPC consortium, and seawater intake and outfall systems as part of the facility. The project ESIA further confirms that ACWA Power's scope includes intake and outfall pipelines sized for the planned future 60 MIGD expansion, with the IWP outfall diffusers positioned close to the Hassyan power-plant diffusers after marine dispersion and environmental review.
Phase: commissioning. Evidence reviewed: 13 July 2026.