Project record

Hawar SWRO offshore intake and outfall tender

Reverse-osmosis membrane vessels shown on EWA's Hawar SWRO project page; an illustrative process image, not a photograph of the proposed plant

Electricity and Water Authority, Bahrain

Bahrain's Electricity and Water Authority has split the New Hawar SWRO scheme into three EPC tenders: the desalination plant, an offshore seawater intake and outfall system, and two storage tanks with forwarding pumps. The first plant is sized at 1 MIGD, while the marine facilities and their auxiliary systems must allow for an ultimate 3 MIGD production capacity. Two bids were opened for the marine package in December 2025. The plant package received ten bids and the storage package received four.

Project signal

Tender in Bahrain

Current status Two bids were opened for Hawar's separate offshore intake and outfall EPC package on 25 December 2025; EWA still lists the wider desalination scheme as a future project and no award is published Source confidence Confirmed

Location

Bahrain / Middle East

Segment

Marine utilities

Status

Two bids were opened for Hawar's separate offshore intake and outfall EPC package on 25 December 2025; EWA still lists the wider desalination scheme as a future project and no award is published / Confirmed

Last checked

18 July 2026

Coverage

Related sectors

Marine utilities is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Electricity and Water Authority, Kingdom of Bahrain
Delivery parties
No marine works contractor selected; Al Hassanain B.S.C. Closed and Noble Development FZ LLC are opened bidders only
Contract route
EWA issued the offshore intake and outfall package as public international RFP 616/2025/BTB (4621/2025/3200). Bahrain Tender Board opened two accepted bids on 25 December 2025: BHD 12,889,343.500 from Al Hassanain B.S.C. Closed and BHD 822,120.631 from Noble Development FZ LLC. Tender Board states that opened bids remain subject to technical and financial evaluation and that the lowest price is not necessarily awarded. No award is published in the official sources reviewed on 18 July 2026.
Execution window
The marine tender states a one-year contract duration. The linked plant tender states two years and the storage-and-pump tender 18 months. These are contract durations from the tender records, not confirmed start or completion dates; none should be sequenced from bid opening without award and notice-to-proceed evidence.
Works package
The marine EPC package covers design, procurement, construction, commissioning and testing of the offshore seawater intake and outfall for the new 1 MIGD SWRO plant. Tender notes state a 1,515 cubic metre per hour intake flow and require the intake, outfall and auxiliary systems to be sized for an ultimate 3 MIGD plant. Separate tender 4622/2025/3200 covers the 1 MIGD desalination plant. Separate tender 4623/2025/3200 covers two welded-steel ground storage tanks of 1 MIG each, forwarding pumps, chlorination and associated works.
Marine interfaces
The intake and outfall are a named offshore construction package rather than an inferred coastal interface. The public notice defines capacity and EPC responsibility but does not publish the alignments, pipe sizes, intake structure, diffuser arrangement, trenching or installation method. Those missing details limit marine-contractor qualification and coordination with the onshore plant.
Commercial evidence boundary
The two opened marine bids differ by more than an order of magnitude. The public table alone does not show whether the values reflect the same technical basis, attachments, exclusions or corrections, so the spread is a reason to wait for evaluation and award documents rather than rank the bidders. The ten plant bids and four storage bids also show that each package has its own competitive field and must be followed independently.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

EWA retained Hawar SWRO in its future-project portfolio

The current owner page confirms a 1 MIGD initial plant and 2 MIG of storage, both extendable, without naming an award or construction start.

Source

Ten bids opened for the desalination plant package

The plant competition is distinct from the offshore and storage tenders; opened-bid status does not establish the EPC contractor.

Source

Two bids opened for the offshore intake and outfall

Tender Board published accepted opened values from Al Hassanain and Noble Development while retaining technical and financial evaluation before award.

Source

Four bids opened for storage tanks and forwarding pumps

The downstream storage and distribution station remained a third EPC competition with its own 18-month duration and acceptance path.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Award decisions and signed scope for tenders 4621/2025/3200, 4622/2025/3200 and 4623/2025/3200
  • Technical and commercial treatment of the two widely separated marine-package bid values
  • Final intake flow, outfall flow, alignments, shore crossings and tie-in points
  • Responsibility matrix between offshore works, the 1 MIGD plant and the storage-and-pump station
  • Marine permits, bathymetry, geotechnical basis and environmental discharge conditions
  • Notice to proceed, marine mobilisation, testing and integrated commissioning evidence

Reporting status

Tender, confirmed confidence

Last checked 18 July 2026 across 7 cited sources. The dated timeline above carries the project events.