Bahrain's Electricity and Water Authority has split the New Hawar SWRO scheme into three EPC tenders: the desalination plant, an offshore seawater intake and outfall system, and two storage tanks with forwarding pumps. The first plant is sized at 1 MIGD, while the marine facilities and their auxiliary systems must allow for an ultimate 3 MIGD production capacity. Two bids were opened for the marine package in December 2025. The plant package received ten bids and the storage package received four.
Project signal
Tender in Bahrain
Current statusTwo bids were opened for Hawar's separate offshore intake and outfall EPC package on 25 December 2025; EWA still lists the wider desalination scheme as a future project and no award is publishedSource confidenceConfirmed
Location
Bahrain / Middle East
Segment
Marine utilities
Status
Two bids were opened for Hawar's separate offshore intake and outfall EPC package on 25 December 2025; EWA still lists the wider desalination scheme as a future project and no award is published / Confirmed
Last checked
18 July 2026
Coverage
Related sectors
Marine utilities is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
Electricity and Water Authority, Kingdom of Bahrain
Delivery parties
No marine works contractor selected; Al Hassanain B.S.C. Closed and Noble Development FZ LLC are opened bidders only
Contract route
EWA issued the offshore intake and outfall package as public international RFP 616/2025/BTB (4621/2025/3200). Bahrain Tender Board opened two accepted bids on 25 December 2025: BHD 12,889,343.500 from Al Hassanain B.S.C. Closed and BHD 822,120.631 from Noble Development FZ LLC. Tender Board states that opened bids remain subject to technical and financial evaluation and that the lowest price is not necessarily awarded. No award is published in the official sources reviewed on 18 July 2026.
Execution window
The marine tender states a one-year contract duration. The linked plant tender states two years and the storage-and-pump tender 18 months. These are contract durations from the tender records, not confirmed start or completion dates; none should be sequenced from bid opening without award and notice-to-proceed evidence.
Works package
The marine EPC package covers design, procurement, construction, commissioning and testing of the offshore seawater intake and outfall for the new 1 MIGD SWRO plant. Tender notes state a 1,515 cubic metre per hour intake flow and require the intake, outfall and auxiliary systems to be sized for an ultimate 3 MIGD plant. Separate tender 4622/2025/3200 covers the 1 MIGD desalination plant. Separate tender 4623/2025/3200 covers two welded-steel ground storage tanks of 1 MIG each, forwarding pumps, chlorination and associated works.
Marine interfaces
The intake and outfall are a named offshore construction package rather than an inferred coastal interface. The public notice defines capacity and EPC responsibility but does not publish the alignments, pipe sizes, intake structure, diffuser arrangement, trenching or installation method. Those missing details limit marine-contractor qualification and coordination with the onshore plant.
Commercial evidence boundary
The two opened marine bids differ by more than an order of magnitude. The public table alone does not show whether the values reflect the same technical basis, attachments, exclusions or corrections, so the spread is a reason to wait for evaluation and award documents rather than rank the bidders. The ten plant bids and four storage bids also show that each package has its own competitive field and must be followed independently.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.