Two bids price Hawar's offshore intake and outfall

Published 18 July 2026 Publisher IMWO Region Middle East Confidence Confirmed
Coastal desalination facility image accompanying TradeArabia's report on the Hawar SWRO tender; the publisher does not identify it as the proposed Hawar site

TradeArabia News Service

Bahrain Tender Board opened two bids for Hawar's separate offshore intake and outfall EPC package on 25 December 2025. The works serve a 1 MIGD SWRO plant but must be sized for an ultimate 3 MIGD production capacity.

Published scope and current milestone

Bahrain Tender Board lists the marine scope, one-year duration, bid count and opened values. The linked plant and storage tender records establish the three-package interface. EWA's current project page keeps the scheme in its future-project portfolio. Bahrain Tender Board has published neither an award nor a construction start.

Marine-system delivery and operating implications

The desalination plant is not one indivisible contract. EWA has separate competitions for the offshore system, the treatment plant and two storage tanks with forwarding pumps. The marine contractor must therefore deliver a tested interface into two other EPC packages, each with a different bidder field and contract duration.

Evidence conclusion

Testing, acceptance and operating evidence

Tender Board has published bidders and opening prices, not an award. Al Hassanain submitted BHD 12.889 million and Noble Development BHD 0.822 million for the marine package, both marked accepted at opening. That spread cannot be explained from the public table, and Tender Board says the lowest price is not necessarily awarded. The evaluation and signed scope are needed before the price gap can be interpreted.

Outstanding evidence

  • Marine-package evaluation and award
  • Awards for the linked plant and storage packages
  • Final intake and outfall alignments, structures and flows
  • Shore crossings, tie-ins and responsibility split between EPC contractors
  • Marine permits, surveys and environmental discharge conditions
  • Notice to proceed, installation method and integrated commissioning sequence

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Sources used 7