Marine Utilities

Two bids price Hawar's offshore intake and outfall

Published 18 July 2026 Editorial responsibility IMWO Region Middle East Confidence Confirmed
EWA's separate 66 kV submarine cable being installed in Hawar's shallow coastal water, shown as local marine-work context rather than the proposed SWRO intake or outfall

Electricity and Water Authority, Bahrain

Bahrain Tender Board opened two bids for Hawar's separate offshore intake and outfall EPC package on 25 December 2025. The works serve a 1 MIGD SWRO plant but must be sized for an ultimate 3 MIGD production capacity.

What changed

Bahrain Tender Board lists the marine scope, one-year duration, bid count and opened values. The linked plant and storage tender records establish the three-package interface. EWA's current project page keeps the scheme in its future-project portfolio. Bahrain Tender Board has published neither an award nor a construction start.

Why it matters

The desalination plant is not one indivisible contract. EWA has separate competitions for the offshore system, the treatment plant and two storage tanks with forwarding pumps. The marine contractor must therefore deliver a tested interface into two other EPC packages, each with a different bidder field and contract duration.

Decision read

What remains open

Tender Board has published bidders and opening prices, not an award. Al Hassanain submitted BHD 12.889 million and Noble Development BHD 0.822 million for the marine package, both marked accepted at opening. That spread cannot be explained from the public table, and Tender Board says the lowest price is not necessarily awarded. The evaluation and signed scope are needed before the price gap can be interpreted.

Next watchpoints

  • Marine-package evaluation and award
  • Awards for the linked plant and storage packages
  • Final intake and outfall alignments, structures and flows
  • Shore crossings, tie-ins and responsibility split between EPC contractors
  • Marine permits, surveys and environmental discharge conditions
  • Notice to proceed, installation method and integrated commissioning sequence

Knowledge context

Related knowledge topics

Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.