Location
United Kingdom / Europe
Project record
Sizewell C Harbour Authority; official project marine works map
Sizewell C Harbour Authority is overseeing three sub-seabed utility lines off the Suffolk coast: a combined drainage outfall for treated construction-site wastewater, a seawater intake for the temporary desalination plant and a return line for surplus seawater. The harbour master's February notice started sequential boring and lining. Separate notices then scheduled the CDO pipe pull for April and the desalination intake and outfall pipe pulls for June. Those two operation-specific notices are now inactive, while the wider three-line construction notice remains active.
United Kingdom / Europe
Marine utilities
Three sub-seabed utility lines remain under an active harbour construction notice; the CDO and desalination pipe-pull notices have closed / Confirmed
20 July 2026
Coverage
Marine utilities is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe harbour register lists Notice 11 as active and the CDO and desalination pipe-pull notices as inactive. This supports completion of the two discrete pull-in windows, while head structures, testing, plant integration and final acceptance remain open.
SourceNotice 24 scheduled approximately 500-metre floating pipes for towage, jack-up-assisted pull-in and diving operations. The notice later moved to the inactive register; it does not certify the complete desalination marine system.
SourceNotice 19 scheduled a 48-72 hour harbour closure around the CDO pull-in using NP497 and associated vessels. Its later inactive status supports the end of that operation, not final outfall acceptance.
SourceNotice 11 set commencement for the CDO, temporary desalination intake and desalination outfall and named the initial vessel spread. The notice remains active on the harbour register.
SourceEvidence gap