Location
United Kingdom / Europe
Project record
Sizewell C Harbour Authority; official project marine works map
Sizewell C Harbour Authority is overseeing three sub-seabed utility lines off the Suffolk coast: a combined drainage outfall for treated construction-site wastewater, a seawater intake for the temporary desalination plant and a return line for surplus seawater. The harbour master's February notice started sequential boring and lining. Separate notices then scheduled the CDO pipe pull for April and the desalination intake and outfall pipe pulls for June. Those two operation-specific notices are now inactive, while the wider three-line construction notice remains active.
United Kingdom / Europe
Marine utilities
Three sub-seabed utility lines remain under an active harbour construction notice; the CDO and desalination pipe-pull notices have closed / Confirmed
20 July 2026
Controlled taxonomy
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Material change register
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
The harbour register lists Notice 11 as active and the CDO and desalination pipe-pull notices as inactive. This supports completion of the two discrete pull-in windows, while head structures, testing, plant integration and final acceptance remain open.
Read controlling sourceNotice 24 scheduled approximately 500-metre floating pipes for towage, jack-up-assisted pull-in and diving operations. The notice later moved to the inactive register; it does not certify the complete desalination marine system.
Read controlling sourceNotice 19 scheduled a 48-72 hour harbour closure around the CDO pull-in using NP497 and associated vessels. Its later inactive status supports the end of that operation, not final outfall acceptance.
Read controlling sourceNotice 11 set commencement for the CDO, temporary desalination intake and desalination outfall and named the initial vessel spread. The notice remains active on the harbour register.
Read controlling sourceDelivery watch
Cancellation or replacement of the active three-line notice, followed by evidence for head-structure installation, as-built surveys, hydraulic and integrity testing, environmental compliance, connection to the temporary desalination plant, first production water and owner acceptance.
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Read featured analysis Review methodology Submit stronger evidence or a correction Open project trackerThe active-notices register keeps Notice 11 in force and places Notices 19 and 24 in the inactive list. Notice 11 covers the three-line boring and lining sequence and names the principal marine plant. Notice 19 scheduled the CDO pipe pull for about 16 April; Notice 24 scheduled two desalination pipe pulls for about 3 June and states that the notice would be cancelled on completion. The harbour programme includes CDO and desalination dredging, pipe installation and head structures. Sizewell C's water page says the temporary desalination plant will supply most construction water against peak demand of four million litres per day. Planning documents provide assessment-stage head locations and removal intent; they are not as-built records.
Phase: construction. Evidence reviewed: 20 July 2026.