Torrent wastewater treatment plant adaptation

Aerial photograph of the Torrent wastewater treatment plant works after the 29 October 2024 DANA, showing concrete treatment structures and flood-affected work areas

Júcar River Basin Authority (CHJ); photograph in the 2025 Technical Directorate report, not evidence of current progress, completion or commissioning

Spain's Directorate-General for Water signed contract 08.346-0683/2111 with the Global Omnium Medioambiente-CICLAGUA-BECSA UTE on 17 July 2023 for EUR 20,793,692.54 excluding VAT. CHJ records the setting-out check on 18 September 2023 and the start of the 30-month execution clock on 19 September 2023; its current works register still lists the adaptation in execution. The 18,000 m3/day design combines conventional aerobic treatment with an anaerobic membrane bioreactor, tertiary treatment, a new sludge line, storm-overflow storage, deodorisation and an agricultural reuse connection. CHJ's 2025 ledger reports EUR 997,242.85 certified against modification 1 and EUR 854,404.65 against emergency lot 1. PLACSP's later 10 August 2026 modification record adds zero euros and zero months. These certified amounts are not contract-value changes, and the post-DANA flood-defence and setback package remains outside the main UTE ledger.

Project signal

Construction in Spain

Current status CHJ currently lists the Torrent adaptation works in execution under the Global Omnium Medioambiente-CICLAGUA-BECSA UTE; its 2025 delivery report fixes the site-start baseline at 19 September 2023 and records separate certified amounts for modification 1 and the post-DANA emergency workfront, while PLACSP's 10 August 2026 modification record adds zero price and zero duration Source confidence Confirmed

Location

Spain / Europe

Segment

Urban wastewater treatment, tertiary reuse and flood resilience

Status

CHJ currently lists the Torrent adaptation works in execution under the Global Omnium Medioambiente-CICLAGUA-BECSA UTE; its 2025 delivery report fixes the site-start baseline at 19 September 2023 and records separate certified amounts for modification 1 and the post-DANA emergency workfront, while PLACSP's 10 August 2026 modification record adds zero price and zero duration / Confirmed

Last checked

12 August 2026

Coverage

Related sectors

Urban wastewater treatment, tertiary reuse and flood resilience is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Spanish Ministry for the Ecological Transition and the Demographic Challenge, Directorate-General for Water / Júcar River Basin Authority (CHJ)
Delivery parties
UTE Global Omnium Medioambiente, S.L. - CICLAGUA, S.A. - BECSA, S.A. - confirmed main works contractor, Aquatec, Proyectos para el Sector del Agua, S.A.U. - confirmed construction-supervision contractor, Post-DANA emergency works contractor - not identified in the cited official sources, Civil, process, membrane, tertiary, sludge, electrical, control and reuse lower tiers - not publicly identified
Contract route
The Directorate-General for Water tendered procedure 08.346-0683/2111 with an estimated value of EUR 26,665,417.47 excluding VAT and received 23 offers. The contract was awarded on 24 May 2023 and signed on 17 July 2023 with the Global Omnium Medioambiente-CICLAGUA-BECSA UTE at EUR 20,793,692.54 excluding VAT and EUR 25,160,367.97 payable. PLACSP published modification 1 on 10 August 2026. Its structured record reports a EUR 0 tax-exclusive modification amount, 0-month duration change, 30-month final duration and EUR 20,793,692.84 final tax-exclusive amount; the EUR 0.30 difference from the formalised award value is preserved as a source discrepancy, not described as commercial growth.
Execution window
Contract 08.346-0683/2111 states 30 months and MITECO's delivery description includes six months of commissioning and functional testing. CHJ's 2025 report records the setting-out check on 18 September 2023 and says the execution period began on 19 September 2023. The nominal contract clock therefore has an official start, but the cited records do not publish the current approved baseline after the 29 October 2024 DANA and redesign. CHJ's August 2026 execution classification and PLACSP's zero-month modification do not by themselves establish delay, approved extension, physical percentage or a revised completion date.
Works package
Adapt the existing Torrent plant, originally developed in the late 1970s and expanded in 1994, for 18,000 m3/day. MITECO's approved-project page gives 150,000 population equivalent, while CHJ's 2025 report gives 105,000 population equivalent at 350 mg/l BOD5; the two stated design loads remain a source discrepancy. The works include inlet and collector interfaces, screening and pumping, an anti-overflow storm tank, pretreatment, an aerobic bioreactor, secondary clarification, an anaerobic membrane bioreactor, tertiary treatment, deodorisation, a new sludge line and connection for agricultural reuse. MITECO reports 403.5 m3/hour peak flow and 1,875 m3/hour maximum flow, with effluent targets of 25 mg/l BOD5, 125 mg/l COD, 35 mg/l suspended solids, 10 mg/l total nitrogen and 1 mg/l phosphorus.
Marine interfaces
This is an inland wastewater and flood-resilience project, not a port, coastal or offshore package. Its relevant waterworks interfaces are live-plant continuity, collector flows, storm-overflow control, biological and membrane treatment, sludge handling, tertiary reuse, flood exposure, relocation or setback of workfronts and commissioning. No marine outfall, dredging, reclamation, quay or offshore installation is evidenced.
Commercial evidence boundary
The main signed works value is EUR 20,793,692.54 excluding VAT and EUR 25,160,367.97 payable, against a EUR 26,665,417.47 excluding-VAT estimate. CHJ's 2025 accounts report EUR 997,242.85 certified for modification 1 and EUR 854,404.65 for emergency lot 1; neither line is a stated package total or variation value. PLACSP's later modification record reports zero price and zero duration change, with a EUR 20,793,692.84 final tax-exclusive figure that is EUR 0.30 above the formalised award row. MITECO separately reports Aquatec's supervision contract at EUR 801,885.15. CHJ estimates the emergency scope at EUR 6.0 million, while MITECO gives approximately EUR 6.2 million; retain both as dated source snapshots and do not merge either into the main UTE contract.

Contract and delivery chain

Named roles and open packages

Named appointments are shown against the workstream they cover. Unallocated packages remain open until a project source identifies the responsible party.

Main adaptation works

08.346-0683/2111 Torrent sanitation and treatment-system adaptation

Named party
UTE Global Omnium Medioambiente-CICLAGUA-BECSA
Status
Confirmed
Source position
MITECO and PLACSP confirm the 17 July 2023 contract, EUR 20,793,692.54 excluding-VAT award value and 30-month term. CHJ records the setting-out check on 18 September 2023 and execution-period start on 19 September 2023. Source
Construction supervision

Works control and supervision

Named party
Aquatec, Proyectos para el Sector del Agua, S.A.U.
Status
Confirmed
Source position
MITECO reports a EUR 801,885.15 supervision contract dated 27 June 2023. Source
Treatment and reuse systems

Aerobic treatment, AnMBR, tertiary, sludge, deodorisation and agricultural reuse

Named party
Main UTE; lower-tier suppliers undisclosed
Status
Confirmed
Source position
MITECO's approved project description defines the 18,000 m3/day, 150,000-population-equivalent process and reuse scope. Source
Contract modification

Modification 1 under 08.346-0683/2111

Named party
Directorate-General for Water and main UTE
Status
Confirmed
Source position
PLACSP's 10 August 2026 structured record reports EUR 0 price change, 0-month duration change and a 30-month final duration. CHJ separately records EUR 997,242.85 certified against modification 1 during 2025; that annual certification is not a stated variation value. Source
Post-DANA flood resilience

Flood defence and setback of the Torrent adaptation works

Named party
MITECO / CHJ; delivery contractor undisclosed
Status
Confirmed
Source position
The separate package was declared on 28 May 2025. CHJ estimates emergency lot 1 at EUR 6.0 million and records EUR 854,404.65 certified during 2025; MITECO separately reports approximately EUR 6.2 million. None of those figures belongs in the main UTE total. Source
Progress and acceptance

Installed quantities, commissioning and completion

Named party
Owner, UTE and supervisor
Status
Not evidenced
Source position
CHJ confirms only that the works remain in execution; no cited source supplies physical percentage, installed quantities, test results, completion or acceptance.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

PLACSP publishes modification 1

The structured record adds zero euros and zero months, preserves a 30-month final duration and leaves the modification reason and physical status unexplained.

Source

MITECO declares a separate post-DANA emergency package

Flood defence and setback of the adaptation works becomes a distinct approximately EUR 6.2 million interface rather than an assumed addition to the main UTE contract.

Source

Main execution clock starts

CHJ's 2025 delivery report fixes the setting-out check on 18 September 2023 and the contract execution-period start on 19 September 2023, replacing the earlier unknown-start assumption without establishing the post-DANA baseline.

Source

Main works contract is signed

The Directorate-General for Water formalises the 30-month EUR 20.794 million excluding-VAT contract with the three-company UTE, establishing the legal works package but not its operative site-start date.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Executed modification 1 instrument and reason
  • Approved post-DANA baseline and current programme
  • Current physical progress by treatment workfront
  • AnMBR, tertiary, sludge, pumping, electrical and control suppliers
  • DANA emergency contractor, exact scope and interface with the UTE
  • Flood-defence, setback and land-access approvals
  • Commissioning, functional tests and effluent-performance evidence
  • Agricultural-reuse connection, completion and acceptance
  • Cumulative certified expenditure, variations and final account

Reporting status

Construction, confirmed confidence

Last checked 12 August 2026 across 7 cited sources. The dated timeline above carries the project events.

Last checked 12 August 2026 Cited sources 7