Project record

Algarve seawater desalination intake and outfall system

Portuguese environment minister and project team viewing the Algarve desalination plant model and aerial marine alignment map on 8 July 2026

Sara Matos / Government of Portugal

Águas do Algarve has started the design-build-operate contract for mainland Portugal's first seawater desalination plant. The system combines two intake towers about 2 km offshore, two large-diameter intake pipelines, a 2.13 km brine outfall, a coastal pumping station and a 4.8 km raw-water main to a 16 million m3/year first-stage plant.

Project signal

Construction in Portugal

Current status Construction was released on 22 April 2026 and the site milestone was held on 8 July; offshore intake and outfall execution remains unverified Source confidence Confirmed

Location

Portugal / Europe

Segment

Marine utilities

Status

Construction was released on 22 April 2026 and the site milestone was held on 8 July; offshore intake and outfall execution remains unverified / Confirmed

Last checked

18 July 2026

Coverage

Related sectors

Marine utilities is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Águas do Algarve, S.A.
Delivery parties
ACE Água para o Algarve: GS Inima, Aquapor and Luságua
Contract route
A mixed design, construction and operation contract signed with ACE Água para o Algarve. Águas do Algarve records €102.785 million for design and construction through provisional acceptance and €5.138 million for three years of operation, within a €107.923 million total contract.
Execution window
The contract allows 1,115 days from signature to provisional acceptance, followed by a 1,095-day operating period. Construction release was signed on 22 April 2026 and the symbolic first brick was placed on 8 July; the offshore installation start and accepted first-water date are not published.
Works package
Design and build a 500 l/s seawater reverse-osmosis system prepared for 750 l/s, including two offshore intake towers, DN1000 and DN1200 HDPE intake conduits, the EE1 raw-water pumping station, a roughly 4.8 km DN1200 main to the plant, a DN1200/DN1000 brine route extending 2.13 km offshore, treatment and energy-recovery systems, treated-water connection and three years of operation after provisional acceptance.
Marine interfaces
The marine works place two screened intake structures about 2 km offshore and connect them to the coastal pumping station through separate large-diameter pipelines. The brine return runs roughly 2.13 km offshore and requires a controlled dispersion and monitoring regime. Environmental records also anticipate seabed preparation and dredging around the intake structures and trenched sections.
Commercial evidence boundary
The principal contract is already awarded. Near-term supplier demand covers offshore survey and setting-out, marine plant, trenching and seabed preparation, large-diameter HDPE handling, intake structures, diffuser and protection works, environmental monitoring, testing and commissioning. Public sources do not disclose the marine subcontracting plan or package values.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

The first brick marked the site start

Águas do Algarve and the Portuguese government recorded the on-site ceremony and monitoring committee. The owner calls the event symbolic and does not report offshore plant mobilisation, pipeline installation or first water.

Source

The owner signed the construction release

The release followed APA review of pre-start conditions under the DCAPE. It advances the whole contract into construction but leaves the offshore sequence and physical marine progress to later evidence.

Source

Environmental conformity remained subject to controls

The owner records a favourable execution-design conformity decision conditioned on mitigation, monitoring and compensation. The decision closed a regulatory gate without proving that construction or offshore installation had begun.

Source

The mixed design-build-operate contract was signed

Águas do Algarve fixed the delivery consortium, €107.923 million total and marine system baseline. The contract includes three years of operation after provisional acceptance rather than immediate operating responsibility.

Source

APA issued a conditional environmental decision

The study-stage decision required a later execution-design conformity review and additional marine safeguards. It did not authorize the project to be reported as under construction at that time.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Final construction programme for the offshore intake and brine-return routes
  • Marine plant, seabed preparation and trenching mobilisation
  • Fabrication, tow-out and installation of the two intake towers
  • Placement and connection of the two intake pipelines and 2.13 km outfall
  • Sediment, fisheries, salinity-plume and discharge monitoring during construction
  • Pressure testing, flushing, diffuser checks and integrated wet commissioning
  • Provisional acceptance before the three-year operating period begins
  • First verified 500 l/s production and later evidence for the 750 l/s expansion

Reporting status

Construction, confirmed confidence

Last checked 18 July 2026 across 6 cited sources. The dated timeline above carries the project events.

Last checked 18 July 2026 Cited sources 6