Project record
Águas do Algarve has started the design-build-operate contract for mainland Portugal's first seawater desalination plant. The system combines two intake towers about 2 km offshore, two large-diameter intake pipelines, a 2.13 km brine outfall, a coastal pumping station and a 4.8 km raw-water main to a 16 million m3/year first-stage plant.
Portugal / Europe
Marine utilities
Construction was released on 22 April 2026 and the site milestone was held on 8 July; offshore intake and outfall execution remains unverified / Confirmed
18 July 2026
Controlled taxonomy
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Material change register
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
Águas do Algarve and the Portuguese government recorded the on-site ceremony and monitoring committee. The owner calls the event symbolic and does not report offshore plant mobilisation, pipeline installation or first water.
Read controlling sourceThe release followed APA review of pre-start conditions under the DCAPE. It advances the whole contract into construction but leaves the offshore sequence and physical marine progress to later evidence.
Read controlling sourceThe owner records a favourable execution-design conformity decision conditioned on mitigation, monitoring and compensation. The decision closed a regulatory gate without proving that construction or offshore installation had begun.
Read controlling sourceÁguas do Algarve fixed the delivery consortium, €107.923 million total and marine system baseline. The contract includes three years of operation after provisional acceptance rather than immediate operating responsibility.
Read controlling sourceThe study-stage decision required a later execution-design conformity review and additional marine safeguards. It did not authorize the project to be reported as under construction at that time.
Read controlling sourceDelivery watch
Confirm offshore mobilisation and the approved intake and outfall construction sequence, then follow installed quantities, environmental monitoring, pressure and hydraulic tests, provisional acceptance and first sustained 500 l/s production.
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Read featured analysis Review methodology Submit stronger evidence or a correction Open project trackerÁguas do Algarve's 22 October 2024 contract record controls the €107.923 million total, the split between design-construction and three-year operation, the 1,115-day and 1,095-day periods, the 500 l/s first stage, 750 l/s future provision, two offshore intake towers, twin intake conduits, 4.8 km raw-water main and 2.13 km brine outfall. The owner says APA's 25 November 2025 DCAPE remained conditional on mitigation, monitoring and compensation, and that construction release was signed on 22 April 2026. The 8 July first-brick event is a real site milestone but is described by the owner as symbolic. Government and owner releases do not establish offshore mobilisation, installed towers or pipelines, completed diffuser works, first water, provisional acceptance or environmental performance. APA's earlier conditional decision and study record define the seabed-preparation, dredging, sediment and brine-monitoring boundary rather than construction progress.
Phase: construction. Evidence reviewed: 18 July 2026.