Location
Oman / Middle East
Project record
Ghubrah III is a 300,000 m3/day seawater reverse-osmosis plant under construction in Muscat. Its marine system comprises two 2,000 mm intake lines, two 1,600 mm discharge lines, an offshore intake tower and a diffuser. Nama PWP's latest annual report targets commercial operation in Q1 2027. Public construction updates confirm an active site, but they do not quantify installed offshore pipe, tower or diffuser work.
Oman / Middle East
Marine utilities
Under construction; Nama PWP targets commercial operation in Q1 2027 / Confirmed
20 July 2026
Controlled taxonomy
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Material change register
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
The event brought together more than 1,250 project and subcontractor personnel and confirms a large active construction site. It does not state offshore installation quantities, mechanical completion, first water or owner acceptance.
Read controlling sourceThe latest owner annual report lists Ghubrah III under construction at 300,000 m3/day with scheduled commercial operation in Q1 2027, superseding the earlier 2026 programme dates without proving a new accepted completion date.
Read controlling sourceThe detailed design defines three screened intake channels and their control equipment. IFC completion authorises a construction basis; it is not evidence that the building, screens, pumps or marine tie-ins were installed.
Read controlling sourceThe agreement fixed Capital Desalination Company as the project vehicle and the 300,000 m3/day capacity. Contract signature preceded construction and does not establish notice to proceed, marine mobilisation or completion.
Read controlling sourceDelivery watch
Dated evidence of installed intake and outfall pipeline lengths, intake-tower and diffuser placement, shore and screening-building tie-ins, followed by hydraulic testing, wet commissioning, first water, owner acceptance and scheduled commercial operation.
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Read featured analysis Review methodology Submit stronger evidence or a correction Open project trackerNama PWP signed the project agreement with Capital Desalination Company in February 2024. Its annual reporting says construction began in 2024 and now targets Q1 2027 commercial operation. GS Inima reported four million work hours without a lost-time injury on 4 May 2026, with more than 1,250 workers and subcontractor personnel at the event. That confirms the scale of site activity, not marine completion. PROES publishes the intake and discharge geometry; Savener publishes completion of the intake-building IFC design. Neither design record establishes installed quantities or accepted operation.
Phase: construction. Evidence reviewed: 20 July 2026.