Ghubrah III construction targets Q1 2027 operation
Savener; exact Ghubrah III intake-building IFC design, not a construction progress image
Nama PWP still targets Q1 2027 commercial operation for Oman's 300,000 m3/day Ghubrah III plant. The four-line marine system is well defined on paper, but current public updates do not say how much of the intake and outfall network has been installed or accepted.
What changed
Nama PWP's latest annual report lists Ghubrah III under construction with scheduled commercial operation in Q1 2027. Its older 2023-2029 statement had placed 150,000 m3/day of early water in summer 2026 and full operation in the second half of 2026. PROES publishes the four FRP pipeline lengths, diameters and offshore structure depths. Savener records completion of the intake-building IFC design. GS Inima's 4 May 2026 safety update confirms a large active construction workforce but gives no marine installation quantities or completion claim.
Why it matters
Four offshore pipelines make this much larger than a single shoreline connection. The system includes two 1,246 m intake lines, two 1,493.92 m discharge lines, an offshore intake tower, a diffuser and a three-channel screening building. Together the lines total about 5.48 km. Any late tower, diffuser, tie-in or hydraulic-test issue can hold back first water even if the process plant looks advanced.
Decision read
What remains open
Keep the project in construction until the record moves from design geometry and site activity to installed and tested marine assets. The decisive documents will be as-built pipeline lengths and surveys, tower and diffuser placement, tie-in and hydraulic-test records, first-water evidence and Nama PWP's acceptance of commercial operation.
Next watchpoints
- Installed lengths and as-built surveys for the two intake and two discharge lines
- Intake-tower and diffuser placement and connection
- Screening-building, shore-crossing and pump tie-ins
- Hydraulic testing, flushing and wet commissioning
- First water and pre-commercial output
- Brine dispersion and receiving-water compliance
- Nama PWP acceptance of Q1 2027 commercial operation
Knowledge context
Related knowledge topics
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Sources used 7
- Nama PWP Annual Report 2025 Nama Power and Water Procurement, 2025
- Water 7-Year Statement 2026-2032 Nama Power and Water Procurement, 2026
- Ghubrah III reaches four million work hours without a lost-time injury GS Inima, 4 May 2026
- Ghubrah III desalination plant intake and discharge systems PROES, 4 September 2023
- Detailed IFC design of the Ghubrah III seawater intake Savener, 18 February 2025
- Nama PWP signed agreement for Ghubrah III desalination plant Nama Power and Water Procurement, 25 February 2024
- Water 7-Year Statement 2023-2029 Oman Power and Water Procurement Company, 2023
Corrections and methodology
Facts are dated to the source record above. IMWO updates the brief when procurement, award, delivery, or scope evidence materially changes.
Review methodology Open intelligence archive Submit a correction