Location
UAE / Middle East
Project record
Taweelah C is a 2.6 GW CCGT project under a signed PPA and a USD 1.687 billion, 32-month EPC contract. Al Jomaih's project-specific staffing records now expose owner-side cooling-water-system review, existing-plant tie-ins, permits, surveys and commissioning interfaces, but they still do not define seawater abstraction, discharge, pipelines, dredging or a marine-civil package.
UAE / Middle East
Marine utilities
PPA and EPC signed; cooling-water review and existing-plant tie-ins exposed, marine route unconfirmed / Reported
16 July 2026
Controlled taxonomy
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Material change register
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
Al Jomaih's Taweelah C BOP role assigns owner-side oversight of the 2.6 GW EPC, surveys and studies, permits, commissioning and tie-ins to the existing plant. This is an execution-interface and staffing signal, not evidence that a tie-in has occurred or that any intake, outfall, pipeline, dredging or marine package exists.
Read controlling sourceThe contractor-side record shows AEW, Sembcorp and Energy China establishing project execution and interface-coordination mechanisms after contract award. This is evidence of contract-performance setup, not site mobilisation, construction commencement, a confirmed cooling-water design, or physical marine works.
Read controlling sourceThe supplier record defines three gas turbines, two steam turbines, five generators and auxiliary systems for the 2.6 GW plant. It confirms the power-island supply chain but does not define cooling-water intake, outfall, dredging, pipeline, shoreline or marine-civil responsibility.
Read controlling sourceThe Hong Kong regulatory filing defines the EPC consortium, price, project-company counterparties and whole-plant design-to-warranty scope. Its broad civil and commissioning language does not identify a separate seawater, cooling-water or marine package, accepted design, permit, or mobilisation date.
Read controlling sourceEWEC confirmed TAQA's 60 per cent project-company stake, the international consortium's 40 per cent stake, a PPA through 2050 and a 2029 commercial-operation forecast. Award and PPA execution establish the development structure; they do not prove financial close, notice to proceed, marine scope or construction progress.
Read controlling sourceA Taweelah C mechanical and piping role requires cooling-water-system knowledge and oversight of EPC piping design, construction testing and handover. The same page describes the plant as inland and uses a 2.4 GW figure that differs from the later 2.6 GW award, so it is role-level interface evidence rather than a controlling design or marine-scope record.
Read controlling sourceThe bid record moved the project from RFP to competitive evaluation and named the three bidding groups. It was not a preferred-bidder decision, award, PPA, EPC contract, or evidence of cooling-water and marine-package definition.
Read controlling sourceThe RFP opened procurement for development, financing, construction, operation, maintenance and ownership of the carbon-capture-ready CCGT plant. The public notice located the project inside the coastal power and desalination complex but did not publish a project-specific cooling-water or marine works package.
Read controlling sourceDelivery watch
A controlled design, ESIA, permit, owner, EPC or package record defining the cooling-water configuration and any physical seawater, discharge, pipeline, dredging, shoreline or marine-civil scope
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Read featured analysis Review methodology Submit stronger evidence or a correction Open project trackerEWEC issued the Taweelah C RFP on 24 July 2024 and received three proposals on 8 September 2025. On 3 June 2026, EWEC awarded the 2.6 GW IPP to TAQA with Aljomaih Energy and Water Company and Sembcorp Industries, signed the PPA through 2050, and forecast commercial operation in 2029. Energy China's 4 June Hong Kong regulatory filing records a USD 1.687 billion EPC contract with a 32-month duration and scope from design and manufacture through civil works, commissioning, acceptance and warranty support. Siemens Energy identified three gas turbines, two steam turbines, five generators and auxiliary systems on 16 June, and Energy China reported the EPC execution meeting, contract-signing ceremony and interface-coordination setup on 17 June. Al Jomaih's 19 December 2025 mechanical role names cooling-water-system knowledge and piping oversight; its 25 June 2026 BOP role names existing-plant tie-ins, permits, surveys, studies and commissioning under the 2.6 GW execution scope. The job pages expose owner-side interface review but are not controlled design documents, and the older page's 2.4 GW description differs from the later award. Seawater abstraction, outfall, discharge route, dredging, cofferdam, pipeline, shoreline crossing, marine contractor, marine permit and marine mobilisation are not defined in the published scope. The nearby Taweelah RO desalination plant and legacy Taweelah facilities remain context only.
Phase: award. Evidence reviewed: 16 July 2026.