Location
UAE / Middle East
Project record
Taweelah C is a 2.6 GW CCGT project under a signed PPA and a USD 1.687 billion, 32-month EPC contract. Al Jomaih's project-specific staffing records now expose owner-side cooling-water-system review, existing-plant tie-ins, permits, surveys and commissioning interfaces, but they still do not define seawater abstraction, discharge, pipelines, dredging or a marine-civil package.
UAE / Middle East
Marine utilities
PPA and EPC signed; cooling-water review and existing-plant tie-ins exposed, marine route unconfirmed / Reported
16 July 2026
Coverage
Marine utilities is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogAl Jomaih's Taweelah C BOP role assigns owner-side oversight of the 2.6 GW EPC, surveys and studies, permits, commissioning and tie-ins to the existing plant. This is an execution-interface and staffing signal, not evidence that a tie-in has occurred or that any intake, outfall, pipeline, dredging or marine package exists.
SourceThe contractor-side record shows AEW, Sembcorp and Energy China establishing project execution and interface-coordination mechanisms after contract award. This is evidence of contract-performance setup, not site mobilisation, construction commencement, a confirmed cooling-water design, or physical marine works.
SourceThe supplier record defines three gas turbines, two steam turbines, five generators and auxiliary systems for the 2.6 GW plant. It confirms the power-island supply chain but does not define cooling-water intake, outfall, dredging, pipeline, shoreline or marine-civil responsibility.
SourceThe Hong Kong regulatory filing defines the EPC consortium, price, project-company counterparties and whole-plant design-to-warranty scope. Its broad civil and commissioning language does not identify a separate seawater, cooling-water or marine package, accepted design, permit, or mobilisation date.
SourceEWEC confirmed TAQA's 60 per cent project-company stake, the international consortium's 40 per cent stake, a PPA through 2050 and a 2029 commercial-operation forecast. Award and PPA execution establish the development structure; they do not prove financial close, notice to proceed, marine scope or construction progress.
SourceA Taweelah C mechanical and piping role requires cooling-water-system knowledge and oversight of EPC piping design, construction testing and handover. The same page describes the plant as inland and uses a 2.4 GW figure that differs from the later 2.6 GW award, so it is role-level interface evidence rather than a controlling design or marine-scope record.
SourceThe bid record moved the project from RFP to competitive evaluation and named the three bidding groups. It was not a preferred-bidder decision, award, PPA, EPC contract, or evidence of cooling-water and marine-package definition.
SourceThe RFP opened procurement for development, financing, construction, operation, maintenance and ownership of the carbon-capture-ready CCGT plant. The public notice located the project inside the coastal power and desalination complex but did not publish a project-specific cooling-water or marine works package.
SourceEvidence gap