Project record

Taweelah C IPP coastal utility interface

AEW, Sembcorp and Energy China representatives at the Taweelah C Independent Power Project EPC contract-signing ceremony in Beijing on 15 June 2026

China Energy Engineering

Taweelah C is a 2.6 GW CCGT project under a signed PPA and a USD 1.687 billion, 32-month EPC contract. Al Jomaih's project-specific staffing records now expose owner-side cooling-water-system review, existing-plant tie-ins, permits, surveys and commissioning interfaces, but they still do not define seawater abstraction, discharge, pipelines, dredging or a marine-civil package.

Project signal

Award in UAE

Current status PPA and EPC signed; cooling-water review and existing-plant tie-ins exposed, marine route unconfirmed Source confidence Reported

Location

UAE / Middle East

Segment

Marine utilities

Status

PPA and EPC signed; cooling-water review and existing-plant tie-ins exposed, marine route unconfirmed / Reported

Last checked

16 July 2026

Coverage

Related sectors

Marine utilities is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Emirates Water and Electricity Company (power offtaker and procurement authority)
Delivery parties
TAQA, Aljomaih Energy and Water Company, and Sembcorp Industries (developer consortium), China Energy International Group, Guangdong Thermal Power Engineering, and Guangdong Electric Power Design Institute (EPC consortium), Siemens Energy (major generation-equipment supplier)
Contract route
Independent power producer award under a power purchase agreement running to 2050
Execution window
Thirty-two-month EPC duration; commercial operation forecast for 2029
Works package
Design, manufacture, supply, factory testing, transport, civil works, installation, commissioning, training, acceptance, warranty, and maintenance during warranty for a 2.6 GW dual-fuel CCGT plant at the Al Taweelah Power and Desalination Complex
Marine interfaces
Project-specific staffing identifies cooling-water-system review and existing-plant tie-ins. The published scope does not define seawater intake, discharge, pipeline, dredging, shoreline or marine-civil works
Commercial evidence boundary
The IPP, EPC and owner-side interface review are evidenced; neither coastal siting nor a cooling-water job requirement establishes an available marine works package

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

Lead developer recruited for BOP execution and existing-plant tie-ins

Al Jomaih's Taweelah C BOP role assigns owner-side oversight of the 2.6 GW EPC, surveys and studies, permits, commissioning and tie-ins to the existing plant. This is an execution-interface and staffing signal, not evidence that a tie-in has occurred or that any intake, outfall, pipeline, dredging or marine package exists.

Source

Energy China reported an EPC execution meeting and contract-signing ceremony

The contractor-side record shows AEW, Sembcorp and Energy China establishing project execution and interface-coordination mechanisms after contract award. This is evidence of contract-performance setup, not site mobilisation, construction commencement, a confirmed cooling-water design, or physical marine works.

Source

Siemens Energy identified the generation-equipment supply package

The supplier record defines three gas turbines, two steam turbines, five generators and auxiliary systems for the 2.6 GW plant. It confirms the power-island supply chain but does not define cooling-water intake, outfall, dredging, pipeline, shoreline or marine-civil responsibility.

Source

Energy China disclosed the USD 1.687 billion EPC contract and 32-month duration

The Hong Kong regulatory filing defines the EPC consortium, price, project-company counterparties and whole-plant design-to-warranty scope. Its broad civil and commissioning language does not identify a separate seawater, cooling-water or marine package, accepted design, permit, or mobilisation date.

Source

EWEC awarded the IPP and signed the power purchase agreement

EWEC confirmed TAQA's 60 per cent project-company stake, the international consortium's 40 per cent stake, a PPA through 2050 and a 2029 commercial-operation forecast. Award and PPA execution establish the development structure; they do not prove financial close, notice to proceed, marine scope or construction progress.

Source

Developer staffing record named cooling-water-system review

A Taweelah C mechanical and piping role requires cooling-water-system knowledge and oversight of EPC piping design, construction testing and handover. The same page describes the plant as inland and uses a 2.4 GW figure that differs from the later 2.6 GW award, so it is role-level interface evidence rather than a controlling design or marine-scope record.

Source

EWEC received three development proposals

The bid record moved the project from RFP to competitive evaluation and named the three bidding groups. It was not a preferred-bidder decision, award, PPA, EPC contract, or evidence of cooling-water and marine-package definition.

Source

EWEC issued the Taweelah C request for proposals

The RFP opened procurement for development, financing, construction, operation, maintenance and ownership of the carbon-capture-ready CCGT plant. The public notice located the project inside the coastal power and desalination complex but did not publish a project-specific cooling-water or marine works package.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Controlled cooling-water basis and whether the system is recirculating, air-cooled, seawater-cooled, or tied to shared infrastructure
  • Environmental and permit documents defining intake, outfall, or coastal interfaces
  • Package boundaries for pipelines, dredging, cofferdams, access, and marine civils
  • Named designers, contractors, tender notices, and awards
  • Marine mobilisation, hydraulic testing, discharge compliance, and commissioning

Reporting status

Award, reported confidence

Last checked 16 July 2026 across 10 cited sources. The dated timeline above carries the project events.

Last checked 16 July 2026 Cited sources 10