Project record

Nacala intake, water-treatment, transmission and pumping works

ARA Norte, World Bank and project personnel at a Nacala water-system construction site in September 2025

ARA Norte, 26 September 2025; official visit to Nacala water-treatment, pumping and elevated-storage construction works

World Bank contract 1765193 identifies Jiangxi Water and Hydropower Construction Group Co., Ltd. under FIPAG/DRIVE/W-15/23 for rehabilitation and construction of Nacala's intake, water-treatment facilities, transmission main and pumping stations. Signature followed on 10 January 2024 at USD 17,984,709.45. ARA Norte's 26 September 2025 site report names the JWHC team and shows the treatment, pumping and elevated-storage works under construction. The December 2025 completion report says two Nacala contracts remained incomplete when the wider project closed on 30 June 2025, continued with Government of the Netherlands financing and were expected to finish in April 2026. No later cited source confirms W-15/23 completion or acceptance.

Project signal

Construction in Mozambique

Current status Jiangxi Water and Hydropower Construction Group signed the USD 17.985 million W-15/23 contract on 10 January 2024; ARA Norte documented work at the treatment, pumping and elevated-storage sites in September 2025, and no package completion or acceptance record follows the cited April 2026 target Source confidence Confirmed

Location

Mozambique / Africa

Segment

Water intake and treatment works

Status

Jiangxi Water and Hydropower Construction Group signed the USD 17.985 million W-15/23 contract on 10 January 2024; ARA Norte documented work at the treatment, pumping and elevated-storage sites in September 2025, and no package completion or acceptance record follows the cited April 2026 target / Confirmed

Last checked

14 August 2026

Coverage

Related sectors

Water intake and treatment works is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
FIPAG under Mozambique's Water Services and Institutional Support Project II; FIPAAS is the statutory successor to FIPAG under Decree 68/2025
Delivery parties
Jiangxi Water and Hydropower Construction Group Co., Ltd. - works contractor under FIPAG/DRIVE/W-15/23, Design reviewer, supervision engineer, mechanical and electrical suppliers, intake and pipeline subcontractors, testing laboratories and commissioning authority - not identified in the cited contract record
Contract route
The March 2025 procurement plan lists a prior-review, open-international Request for Bids and a USD 21.5 million estimate. Contract 1765193 records the later 10 January 2024 signature and USD 17,984,709.45 committed supplier amount. The difference is a procurement-baseline comparison, not proven savings or final cost.
Execution window
The parent project closed on 30 June 2025. ARA Norte documented JWHC and the visiting World Bank mission at the treatment, pumping and elevated-storage work sites on 26 September 2025, but published no completion percentage or test result. The completion report states that two Nacala contracts remained incomplete, continued after closing with Netherlands financing and were expected to finish in April 2026. That expected date has passed; no cited package-level completion, commissioning or acceptance record was found as of 14 August 2026.
Works package
W-15/23 covers rehabilitation and construction of an intake, water treatment, transmission main and pumping stations in Nacala. W-16/23 covers distribution centres and network and remains a separate contract. Public records do not expose W-15/23's unit quantities, treatment-process train, equipment brands, pipeline lengths or capacity accepted at handover.
Marine interfaces
Although this is not a port contract, it is a major coastal-city water-production and conveyance package with intake, treatment, pumping, transmission, power, controls and commissioning interfaces. Safe operation depends on intake performance, process testing, pumping curves, pipeline pressure tests, power reliability, water-quality compliance and integration with the separate distribution package.
Commercial evidence boundary
The USD 17.985 million committed amount is USD 3.515 million below the procurement-plan estimate. Variations, price adjustment, Netherlands continuation-funding allocation, delay entitlement, retention, certified payments and final account remain undisclosed.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

The cited continuation target passed without package closeout evidence

The World Bank ICR expected the two incomplete Nacala contracts to finish in April 2026, but no later cited source confirms W-15/23 completion or acceptance.

Source

Decree 68/2025 created FIPAAS as FIPAG's statutory successor

The decree transferred FIPAG's rights, obligations and resources to the new national water-and-sanitation investment fund. That statutory succession is not evidence of W-15/23 completion, re-award, novation or a new contractor.

Source

ARA Norte recorded JWHC at the Nacala work sites

The official site report and photographs show the treatment, pumping and elevated-storage works under construction during a World Bank mission. The report supplies no completion percentage, commissioning result or acceptance record.

Source

W-15/23 remained incomplete at parent-project closing

The ICR identifies two incomplete Nacala contracts continuing with Netherlands financing and forecasts an April 2026 finish after project closing.

Source

Jiangxi Water and Hydropower signed W-15/23

World Bank contract 1765193 identifies the contractor and reports USD 17,984,709.45 for the intake, treatment, transmission-main and pumping package.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Actual completion and acceptance after April 2026
  • Intake and water-treatment process commissioning
  • Pumping-station performance and power reliability
  • Transmission-main pressure and leakage testing
  • Interface completion with W-16/23 distribution works
  • Netherlands continuation-financing allocation
  • Mechanical, electrical and specialist subcontractors
  • Variations, certified payments and final account

Reporting status

Construction, confirmed confidence

Last checked 14 August 2026 across 7 cited sources. The dated timeline above carries the project events.

Last checked 14 August 2026 Cited sources 7