Location
Jordan / Middle East
Project record
Jordan's National Water Carrier links a 300 million m3/year Red Sea desalination system to marine intake and brine-outfall works at Aqaba, a 438 km buried conveyance pipeline, four pumping stations, regulating tanks, and a 281 MW solar facility.
Jordan / Middle East
Marine utilities
Final technical and legal agreement signed; financial close still pending as of 7 July 2026 / Confirmed
15 July 2026
Controlled taxonomy
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Material change register
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
The ministry said it was continuing efforts to complete financial close and that close would pave the way for implementation. This is the latest public gate: it does not prove notice to proceed, marine mobilisation, accepted final design, physical intake or outfall work, or construction commencement.
Read controlling sourceThe government marked completion of 16 months of technical, legal and financial negotiation and kept financial close and construction launch as later steps. The agreement advances contractual readiness; it is not financial close, a notice to proceed, marine-package mobilisation or physical construction evidence.
Read controlling sourceAIIB approved its financing and set construction-phase environmental and social monitoring expectations. Lender approval contributes to the finance stack but does not establish that all financing conditions are met or that financial close, drawdown, NTP or marine works have occurred.
Read controlling sourceEBRD board approval set out the proposed senior financing and Category A environmental framework. The project remained at Approved rather than Signed or Implementing status, short of financial close or construction release.
Read controlling sourceThe disclosed ESIA package defines the shoreline lagoon, possible cofferdam, nearshore trench, temporary jetty, approximately 3,000 mm outfall, eight-riser diffuser, seabed protection and marine monitoring sequence. Disclosure establishes the assessed design basis, not final design acceptance, permits discharge, construction start or installed marine geometry.
Read controlling sourceThe EIB project record lists five EIB and EU financing or grant signatures through 24 July 2025, totalling EUR 427 million. These commitments support the wider funding plan but do not on their own prove project financial close, NTP or marine construction.
Read controlling sourceThe concession created the project company and assigned long-term financing, construction and operating responsibility. SUEZ explicitly made construction conditional on financial close, leaving mobilisation and physical progress ahead.
Read controlling sourceDelivery watch
Confirm financial close and notice to proceed, then verify marine-construction mobilisation, final intake and outfall design acceptance, environmental monitoring baselines, and the interface schedule linking the Aqaba works to the conveyance and power systems.
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Read featured analysis Review methodology Submit stronger evidence or a correction Open project trackerThe Ministry of Water and Irrigation appointed the Meridiam-SUEZ consortium in 2024, and SUEZ announced a 30-year concession on 15 January 2025 with construction conditional on financial close. EIB's record lists EUR 427 million across five signatures through 24 July 2025. The December 2025 ESIA defines the current marine system and its environmental controls. EBRD approved up to USD 475 million on 25 February 2026 and AIIB approved USD 250 million of nonsovereign financing on 25 March. The government signed the final technical and legal agreement on 21 April after 16 months of negotiations, but the Ministry of Water and Irrigation said on 7 July that it was still working to complete financial close. The current marine design comprises a shoreline intake lagoon excavated to -4 m MSL, possible sheet-piled cofferdams, revetments and seawall protection, a gravity outfall of about 3,000 mm external diameter, nearshore trenching to about 10 m water depth, a temporary aggregate jetty, towed pipe and diffuser installation, backfill, ballast collars and concrete mattresses. Fish recovery, bubble-curtain, oil-boom, turbidity and brine-dispersion controls apply south of the Aqaba Marine Reserve. The indicative 48-month construction period and 2030 operating target are programme intentions, not evidence of notice to proceed or marine mobilisation.
Phase: financing. Evidence reviewed: 15 July 2026.