Project record
Jordan's National Water Carrier links a 300 million m3/year Red Sea desalination system to marine intake and brine-outfall works at Aqaba, a 438 km buried conveyance pipeline, four pumping stations, regulating tanks, and a 281 MW solar facility.
Jordan / Middle East
Marine utilities
Final technical and legal agreement signed; financial close still pending as of 7 July 2026 / Confirmed
15 July 2026
Coverage
Marine utilities is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe ministry said it was continuing efforts to complete financial close and that close would pave the way for implementation. This is the latest public gate: it does not prove notice to proceed, marine mobilisation, accepted final design, physical intake or outfall work, or construction commencement.
SourceThe government marked completion of 16 months of technical, legal and financial negotiation and kept financial close and construction launch as later steps. The agreement advances contractual readiness; it is not financial close, a notice to proceed, marine-package mobilisation or physical construction evidence.
SourceAIIB approved its financing and set construction-phase environmental and social monitoring expectations. Lender approval contributes to the finance stack but does not establish that all financing conditions are met or that financial close, drawdown, NTP or marine works have occurred.
SourceEBRD board approval set out the proposed senior financing and Category A environmental framework. The project remained at Approved rather than Signed or Implementing status, short of financial close or construction release.
SourceThe disclosed ESIA package defines the shoreline lagoon, possible cofferdam, nearshore trench, temporary jetty, approximately 3,000 mm outfall, eight-riser diffuser, seabed protection and marine monitoring sequence. Disclosure establishes the assessed design basis, not final design acceptance, permits discharge, construction start or installed marine geometry.
SourceThe EIB project record lists five EIB and EU financing or grant signatures through 24 July 2025, totalling EUR 427 million. These commitments support the wider funding plan but do not on their own prove project financial close, NTP or marine construction.
SourceThe concession created the project company and assigned long-term financing, construction and operating responsibility. SUEZ explicitly made construction conditional on financial close, leaving mobilisation and physical progress ahead.
SourceEvidence gap