Marine Utilities
Aqaba-Amman switches to existing intake assets and a canyon outfall
IMWO original editorial diagram, based on AAWDCP October 2026 interim assessment
Aqaba-Amman's October marine addendum replaces the proposed new intake lagoon with the existing SEPCO lagoon and pumping station. It relocates the outfall to a canyon and describes a DN2800 HDPE installation with about 20,000 m3 of indicative excavation, including 11,500 m3 requiring onshore disposal.
October design replaces the December 2025 marine construction assumptions
The October 2026 Rev 0 addendum supplies the revised marine design and indicative method. Its existing-approvals statement is attributed to Chapter 9; activity permits still require authority coordination. DFC announced loan and equity-investor insurance approvals on 16 September. EBRD retains Approved status. Financial close, NTP and installed works require current project confirmation. The December 2025 scheme is retained as a dated comparison.
Shore receiving and disposal capacity set part of the offshore production cycle
The revised route addresses bathymetry, diving access and proximity to existing marine assets. Its selected diffuser lies at about 16-27 m depth within the project's 35 m diving limit. Dredging, pipe preparation, ballast, barge movements, shore unloading and truck disposal now need a common daily cycle; the proposed onshore surplus represents 57.5% of excavation.
Evidence conclusion
Fix the port and receiving arrangements before committing the installation spread
The indicative method uses shore work to chainage 60, crane-barge work from 60 to 110 and pipe placement seaward to about chainage 195. Royal Navy Port storage and preparation areas remain under discussion. A tender programme should link ecological release, excavation, shore receiving, pipe-string preparation and installation, with final volumes set by design, ground and the subcontract method. Reusing SEPCO assets also makes tie-in and existing-operation arrangements part of the marine work package.
Outstanding evidence
- Financial close, notice to proceed and marine work-area release
- Existing SEPCO asset condition, intake tie-ins and operating interfaces
- Final canyon-outfall geometry and subcontract construction method
- Royal Navy Port pipe, precast and rock-handling arrangements
- Coral translocation, turbidity controls and onshore receiving/disposal capacity
- Connection, testing and commissioning across marine, desalination, power and conveyance
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 10
- Interim ESIA Addendum Rev 0: revised intake, canyon outfall and construction method AAWDCP, disclosed by EBRD, October 2026; reviewed 24 October 2026
- National Water Carrier loan and equity-investor insurance approval U.S. International Development Finance Corporation, 16 September 2026
- September 2026 board information packet U.S. International Development Finance Corporation, September 2026; Jordan section
- Water ministry confirms financial close remains in progress Jordan News Agency (Petra), 7 July 2026
- Final technical and legal agreement for the National Water Carrier Jordan News Agency (Petra), 21 April 2026
- Aqaba-Amman Water Desalination and Conveyance Project financing approval Asian Infrastructure Investment Bank, 25 March 2026
- Jordan Water Desalination PPP project summary European Bank for Reconstruction and Development, 25 February 2026
- 2025 AAWDC environmental and social impact assessment non-technical summary National Carrier Project Company / JICA disclosure, December 2025
- Thirty-year Aqaba-Amman desalination and conveyance concession SUEZ, 15 January 2025
- Aqaba-Amman desalination and pipeline financing record European Investment Bank, 24 July 2025