Project record

Rietvlei sewage pump station and Bellville WWTW tie-in works

Bellville wastewater treatment works pump-station pipework and treatment-plant interface

City of Cape Town; operating Bellville treated-effluent facility context, not Rietvlei construction or 32Q/2026/27 progress evidence

City of Cape Town contract 32Q/2026/27 invites an open tender for a new 1,100 L/s Rietvlei sewage pump station constructed about 14 m below natural ground level, with a sand trap and automated mechanical screening. The issued scope adds twin approximately 1,980 m DN710 HDPE rising mains to Bellville Wastewater Treatment Works, a new 758 L/s bypass sewage pump station with mechanical screens and vortex degritters at Bellville, and a new Rietvlei administration building. Bids close at 10:00 local time on 2 November 2026; the official record names no awardee or tender value.

Project signal

Tender in South Africa

Current status City of Cape Town tender 32Q/2026/27 is open for a new 1,100 L/s Rietvlei sewage pump station, twin 1,980 m DN710 HDPE rising mains and Bellville WWTW tie-in works; bids close at 10:00 local time on 2 November 2026 and no contractor is appointed Source confidence Confirmed

Location

South Africa / Africa

Segment

Wastewater pump stations, rising mains and treatment-plant tie-ins

Status

City of Cape Town tender 32Q/2026/27 is open for a new 1,100 L/s Rietvlei sewage pump station, twin 1,980 m DN710 HDPE rising mains and Bellville WWTW tie-in works; bids close at 10:00 local time on 2 November 2026 and no contractor is appointed / Confirmed

Last checked

8 August 2026

Coverage

Related sectors

Wastewater pump stations, rising mains and treatment-plant tie-ins is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
City of Cape Town Water and Sanitation Directorate, Distribution Services Department
Delivery parties
Main works contractor - open tender; no awardee named, Ingerop South Africa (Pty) Ltd - tender document compiler; no construction role inferred, HDPE pipeline, excavation and dewatering, mechanical screening, pumping, electrical, controls and commissioning lower tiers - not identified
Contract route
South African Request for Bid (Open-Tender) 32Q/2026/27 under eTenders OCID ocds-9t57fa-164941. The official notice estimates a CIDB 9CE or higher grading, requires a compulsory clarification meeting at 10:00 on 4 September 2026 either at Sarepta Community Hall or online, and makes the subsequent Bellville WWTW site visit non-compulsory. The public six-page issue records a ZAR 300 document-collection fee but no tender estimate.
Execution window
The tender was published on 7 August 2026 and closes at 10:00 local time on 2 November 2026. Later delivery dates remain unconfirmed: the public eTenders record and six-page tender issue reviewed on 8 August establish no award, notice to proceed, construction start, sectional sequence, contract duration, commissioning date or operating handover date.
Works package
The confirmed package combines a deep new Rietvlei sewage pump station rated at 1,100 L/s, sand trap, automated mechanical screening, twin approximately 1,980 m DN710 HDPE rising mains to Bellville WWTW, a new 758 L/s bypass sewage pump station with mechanical screens and vortex degritters at Bellville, associated tie-ins and a new administration building at Rietvlei. The public issue does not expose the full 580-page bills, detailed drawings, temporary works, quantities, power demand, pump configuration, bypass sequence, testing schedule or acceptance criteria.
Marine interfaces
This is an inland municipal wastewater project rather than a marine outfall or coastal construction package. Its waterworks interfaces sit across deep excavation, groundwater and temporary works, large-diameter pressure conveyance, live-sewer isolation and bypass, treatment-plant hydraulic integration, screening and grit removal, electrical and control systems, commissioning and return to service. No ocean outfall, dredging, offshore installation or port scope is evidenced.
Commercial evidence boundary
The January 2026 City capital adjustments budget lists ZAR 879,340,603 as total project or programme cost and says detailed design was complete while the scope was amended for minor Bellville WWTW upgrades. The eTenders release records a zero-value field rather than a procurement value. Supplier positioning therefore depends on the controlled bills and drawings, not on converting the capital programme cost into a contract estimate.

Contract and delivery chain

Named roles and open packages

Named appointments are shown against the workstream they cover. Unallocated packages remain open until a project source identifies the responsible party.

Works procurement

32Q/2026/27 Rietvlei pump station, rising mains and Bellville tie-ins

Named party
City of Cape Town
Status
Confirmed
Source position
The official eTenders release records an active open works tender published 7 August 2026 with a 2 November closing date and no award. Source
Rietvlei pump station

New 1,100 L/s deep sewage pump station, inlet works and administration building

Named party
Works contractor to be selected
Status
Confirmed
Source position
The City tender notice specifies construction about 14 m below natural ground, a sand trap, automated mechanical screening and a new administration building. Source
Pressure conveyance

Twin approximately 1,980 m DN710 HDPE rising mains

Named party
Works contractor and pipeline lower tiers to be selected
Status
Confirmed
Source position
The issued tender notice fixes two DN710 HDPE mains from Rietvlei to Bellville WWTW, each approximately 1,980 m long. Source
Bellville treatment-plant interface

New 758 L/s bypass pump station, screens, vortex degritters and tie-ins

Named party
Works contractor and electromechanical lower tiers to be selected
Status
Confirmed
Source position
The tender notice identifies a new bypass sewage pump station and treatment-headworks equipment at Bellville WWTW. Source
Capital baseline

Rietvlei Pump Station and Rising Main programme

Named party
City of Cape Town
Status
Confirmed
Source position
The January 2026 capital adjustments budget records ZAR 879,340,603 total project or programme cost and a completed detailed-design stage, without setting the tender or award value. Source
Award and delivery

Prime award, lower tiers, construction, testing and acceptance

Named party
No works contractor appointed
Status
Not evidenced
Source position
The procurement remains open and publishes no awardee, contract value, mobilisation, installed quantity, test, commissioning or acceptance record.

Evidence gap

What remains unverified

Outstanding evidence

  • 4 September 2026 compulsory clarification meeting and subsequent addenda
  • 2 November 2026 tender close, opening and evaluation outcome
  • Awardee, contract value, contract duration and notice to proceed
  • Controlled bills, drawings, pump configuration and temporary-works design
  • Deep excavation, groundwater control and live-flow bypass sequence
  • Twin DN710 HDPE supply, jointing, testing and treatment-plant tie-ins
  • Named pumps, screening, degritting, electrical, controls and commissioning suppliers
  • Hydraulic capacity tests, environmental compliance, handover and operating acceptance

Reporting status

Tender, confirmed confidence

Last checked 8 August 2026 across 5 cited sources. The dated timeline above carries the project events.

Last checked 8 August 2026 Cited sources 5

Sources and related records

Read featured analysis Methodology Submit a correction Project tracker

Project sources 5