Award Boundary
Tumaco deepening contract awaits supervision and mobilisation records
Gobernacion de Narino signed Tumaco Phase I access-channel deepening contract GN2862-2026 with Consorcio Puerto Tumaco II for COP 26.826 billion on 22 July. SECOP confirms the 75/15/10 legal member chain, but the contract has no public start date, invoice or payment and the COP 999.999 million independent-supervision process remains unawarded. The evidence supports award, not mobilisation or dredging progress.
The third public procurement iteration now has a signed contract
SECOP II controls the works award, contract, member composition, file inventory and current unawarded supervision process. The public archive retrieval endpoint did not make the named technical files readable during review, so design geometry and quantities remain open. Historic maintenance figures are separate context. No cited source proves mobilisation, field work, dredger assignment, member self-performance or lower-tier subcontracting.
The control package still trails the works award
LP008-2026 follows two earlier SECOP portfolios that show no award. The current record resolves the prime-contract and consortium identities, yet the operational chain stops there. Without a notice to proceed, supervision appointment, dredger, baseline survey or accessible technical annex, treating the project as active dredging would collapse procurement status into field status.
Evidence conclusion
Field start remains unconfirmed after contract signature
Outstanding evidence
- Works notice to proceed and ledger start date
- Independent-supervision award and mobilisation
- Accessible technical annex and priced bill
- Dredger, operator, support fleet and survey team
- Baseline bathymetry, design depth and dredge volume
- Material destination and environmental controls
- Member work allocation and lower-tier appointments
- First certified quantity, invoice and payment
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 6
- SECOP II electronic contract CO1.PCCNTR.9676860 Agencia Nacional de Contratacion Publica / Datos Abiertos Colombia, Signed 22 July 2026
- SECOP II procurement process CO1.BDOS.10262208 Agencia Nacional de Contratacion Publica / Datos Abiertos Colombia, Current awarded process reviewed 6 August 2026
- SECOP II provider group 736836628 Agencia Nacional de Contratacion Publica / Datos Abiertos Colombia, Group registered 18 June 2026
- SECOP II procurement-file inventory for CO1.BDOS.10262208 Agencia Nacional de Contratacion Publica / Datos Abiertos Colombia, Files uploaded May-July 2026
- SECOP II supervision process CO1.BDOS.10370760 Agencia Nacional de Contratacion Publica / Datos Abiertos Colombia, Published 24 June 2026; unawarded at review
- Prior-consultation and environmental preparation for Tumaco channel deepening Ministerio de Transporte / INVIAS, 20 June 2022