Award-chain reconciliation
Manson's Berths 238-239 award resolves 12 subcontract packages
Port of Los Angeles; exact Specification 2792A bid-stage contractor, subcontractor and supplier list
Los Angeles RAMP displays the USD 27,414,900 opportunity amount on 13 award-participant rows, but the Port of Los Angeles contractor attachment resolves the structure: Manson is the prime and 12 named subcontractors carry bid-stage packages totaling USD 3,331,945, or 12.15% of the bid. Johnson-Peltier's USD 1,530,000 electrical package is the largest lower-tier line. The Port's January 2026 capital report separately records the owner project at 22% construction completion through November 2025.
Twelve named lower tiers explain USD 3.332m of the award
The Port's Transmittal 3 lists the bid-stage lower-tier names, roles, amounts and participation arithmetic. The board report and resolution record the prime award, contingency and scope. The January 2026 CIP report gives owner-reported project progress and the project-cost baseline through November 2025. RAMP identifies the opportunity and Contract 2326, but its repeated full-opportunity values are not package amounts and are never summed.
Repeated RAMP amounts require package-level reconciliation
RAMP identifies Contract 2326, but its 13 participant rows repeat the full opportunity amount and do not identify package scopes. Summing those rows would overstate the award by a factor of 13. The Port's signed award record and attached contractor list distinguish the prime contract from lower-tier bid commitments, while the later capital report provides a current project-level progress baseline without proving that every subcontractor has mobilised.
Evidence conclusion
Executed lower-tier evidence remains outstanding
The 12 subcontract lines total exactly USD 3,331,945 and match the Port's reported 12.15% subcontractor share. Manson's prime amount including supplier is USD 24,082,955 and the attachment lists no supplier, so prime plus subcontractors reconciles to the USD 27,414,900 bid without another supplier addition. The largest packages are Johnson-Peltier electrical at USD 1,530,000, Penhall partial demolition at USD 505,250 and Pacific Steel Group reinforcing steel at USD 319,000. SBE subcontract value is USD 2,507,695, or 9.15%, and VSBE value is USD 827,695, or 3.02%. The January 2026 CIP report records 22% construction completion through November 2025, a 31 March 2027 forecast finish, USD 39,288,466 projected project cost and USD 6,315,074 spent. Those owner project figures are broader than Manson's USD 27.415 million bid and USD 30.156 million authorization including contingency. The 22% is project-level progress, not evidence that each lower tier has executed, mobilised or completed 22% of its package.
Outstanding evidence
- Executed subcontract status and any lower-tier substitutions
- Johnson-Peltier electrical mobilisation, installation and testing
- Penhall demolition and Pacific Steel reinforcing-steel quantities
- W.W. Stephenson landside mooring-anchor installation
- Phamarine diving scope and accepted work records
- Pile dynamic analysis, survey and environmental-monitoring deliverables
- Progress split between Berth 238 structures and Berths 167-169 dredging
- PBF tenant topside interface and tie-in readiness
- MOTEMS inspection, commissioning and operating acceptance
- Actual lower-tier payments, SBE and VSBE achievement, changes and final account
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 5
- Contractor, subcontractor and supplier list Port of Los Angeles, Board attachment reviewed 11 August 2026
- Award and approval board report, Specification 2792A Port of Los Angeles, 10 April 2025
- April 2025 Harbor Commission agenda and Resolution 25-10528 Port of Los Angeles Board of Harbor Commissioners, 24 April 2025
- January 2026 Capital Improvement Program report Port of Los Angeles, 29 January 2026; actuals through November 2025
- RAMP Opportunity 217922 award detail City of Los Angeles Regional Alliance Marketplace for Procurement, Award record 24 April 2025; modified 17 June 2025