USACE reports that construction measurements along the completed Freedom Park fish passage kept river-edge velocities below the emerald shiner swimming threshold. Staff also observed shiners moving through the 778-foot structure in the hundreds. The result supports the hydraulic design, while seasonal biological performance, formal structural acceptance and long-term durability remain unverified.
Evidence boundary: USACE reports a project-specific hydraulic measurement and early fish observations after construction. The public record omits the measurement dataset, formal acceptance, seasonal passage counts, population effects, structural condition history and independent ecological review.
United States / Americas
Construction complete; initial hydraulic and biological observations reported
Early hydraulic and biological observations
23 July 2026
Scope and limits
The 23 July 2026 USACE completion release confirms the combined 778-foot structure, May construction finish, measured velocities below the emerald shiner swimming threshold and observations of shiners using the passage. Earlier USACE releases establish the demonstration design, full-phase wall repairs and concrete-filled baffles. The reviewed sources do not publish raw hydraulic measurements, a completion certificate, independent fish counts, a representative monitoring period or post-winter condition evidence.
Confirmed
Still unverified
Metric observations
USACE says field measurements during construction kept velocities below the shiner swimming threshold, while the underlying measurement series is not public.
Shiners were observed moving through in the hundreds, but no seasonal count, control comparison or population trend has been published.
The 778-foot combined structure and May 2026 construction finish are reported, while formal acceptance, as-built and defect-closeout records remain unavailable.
No post-winter inspection, repair history, condition rating or funded maintenance cycle is yet public for the wall repairs, steel plate and baffles.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
The project page tracks the USD 13.4 million programme, Bidco Marine Group contract, 78-foot demonstration, 700-foot full phase and river-facing seawall scope. The companion brief explains why construction completion closes delivery but leaves biological and maintenance monitoring open.
Open project record Read related intelligence brief Explore performance evidenceThe record is limited to the cited public evidence and does not confer certification, ranking, warranty, safety or environmental approval, recognition, or procurement endorsement.