Analysis

Rabigh 4 completes 600,000 m3/day EPC performance test

Published 20 July 2026 Updated 16 August 2026 Publisher IMWO Section Analysis
Rabigh 4 project team marking completion of the desalination plant performance test in February 2026

SEPCOIII / PowerChina

SEPCOIII reports that Rabigh 4 completed its EPC performance test at 600,000 m3/day on 19 February 2026, with power use of 2.712 kWh/m3 before photovoltaic offset. SWPC has not published commercial-operation acceptance, and the marine close-out file remains unavailable.

Rated output was reached on 19 February

SEPCOIII says Rabigh 4 completed its performance test on 19 February 2026 at the plant's 600,000 m3/day design capacity. The contractor reported specific power use of 2.712 kWh/m3, or 2.659 kWh/m3 after photovoltaic generation. The notice fixes the date, output and energy basis of an integrated EPC test.

Saudi Water Partnership Company is the offtaker whose acceptance governs the water-purchase term. No SWPC commercial-operation certificate or equivalent owner notice is public, so Rabigh 4 remains in commissioning for now.

Milestone authority and scope

Contract authority and tested scope determine milestone status

A contractor test, owner certificate, as-built marine record and operating series establish different parts of the plant's technical and commercial status.

  1. 01

    Contractual authority of the issuer

    The EPC contractor, developer, owner, offtaker, regulator, lender and independent evaluator each have authority over different technical or commercial decisions.

    The issuing party defines which milestone the evidence can establish.
  2. 02

    Boundary of the reported test

    Tested block, duration, output, water quality, energy basis, operating mode and included shared systems define the performance claim.

    The result applies only to the equipment, duty and period covered by the test.
  3. 03

    As-built marine system

    Final surveys, alignments, levels, structures, joints, pressure or leak tests, intake availability, outfall hydraulics and diffuser condition describe the permanent sea connection.

    As-built and integrity records establish the delivered marine asset.
  4. 04

    Integrated plant availability

    Treatment trains, intake, outfall, power, storage, transfer and control systems must operate together at the accepted duty.

    Shared assets and downstream interfaces support the declared plant capacity.
  5. 05

    Commercial and contract acceptance

    Provisional acceptance, completion certificates, commercial-operation certificates and operating releases record the accountable party's decision and any unresolved conditions.

    Contract acceptance establishes the commercial milestone.
  6. 06

    Sustained operating performance

    Repeat output, availability, downtime, intake condition, discharge quality, plume behaviour, maintenance and measured user outcomes describe performance after handover.

    Operating and environmental series extend a single test into a service record.

Five public milestones

Issuer authority changes the meaning of each milestone

A test, first water, block commissioning, commercial operation and completed civil works each close a different part of the delivery chain.

Saudi Arabia Confirmed

Rabigh 4 IWP intake, outfall and storage system

Public milestone
EPC performance test at 600,000 m3/day
What it establishes
The contractor reports rated plant output and specific power use through an integrated test period.
Outstanding public record
SWPC commercial-operation confirmation, final marine handover, storage availability, as-built records and receiving-water acceptance.
UAE Confirmed

Hassyan IWP seawater intake and outfall programme

Public milestone
Block A commissioned at 60 MIGD
What it establishes
A named block entered DEWA's installed-capacity record while the 180 MIGD first phase remains in staged delivery.
Outstanding public record
Remaining 120 MIGD, full shared intake-outfall acceptance, diffuser performance and sustained marine water-quality compliance.
Chile Confirmed

Codelco Northern District desalinated water supply marine works

Public milestone
First water at Radomiro Tomic
What it establishes
The connected coast-to-mine route carried desalinated water during progressive commissioning and interface validation.
Outstanding public record
Accepted rated flow and quality, marine-system reliability, all-division service, owner acceptance and BOOT service commencement.
UAE Confirmed

Taweelah RO desalination intake and outfall system

Public milestone
Commercial operations from Q1 2024
What it establishes
ACWA's current profile supports an operating classification for the full 200 MIGD plant.
Outstanding public record
Final intake and outfall geometry, completion surveys, accepted diffuser results and current marine asset condition.
Kiribati Confirmed

South Tarawa sanitation and three-ocean-outfall rehabilitation

Public milestone
Civil completion followed by testing and commissioning
What it establishes
ADB records three completed ocean outfalls and a physically completed sanitation project.
Outstanding public record
Sustained water-quality outcomes, service coverage, maintenance capability, monitoring continuity and operating reliability.

The marine close-out remains unpublished

Modern Marine's project record gives the seawater system a 1,500,000 m3/day intake and a 900,000 m3/day outfall. Both flows exceed product-water output because the process draws feedwater and returns a concentrated stream. Running the plant at full output required that system, but SEPCOIII's notice publishes no marine close-out detail.

Final alignment and levels, intake-screen and pump availability, pipe integrity, diffuser condition, outfall hydraulics, as-built surveys and environmental acceptance are still absent from the public file. Storage availability, punch-list closure and long-run receiving-water performance also sit outside the reported power-use result.

Hassyan and SADDN mark two other commissioning stages

DEWA has placed Hassyan Block A, the first 60 MIGD, in its installed-capacity record. Another 120 MIGD remains in delivery. Full-phase acceptance will cover the remaining blocks together with the shared intake, outfall and diffuser system.

SADDN reached a different point when desalinated water arrived at Codelco's Radomiro Tomic reservoir. Water had crossed the Pacific intake, treatment plant, pumping stations and more than 160 km of high-head conveyance. Techint described progressive commissioning and interface validation, with accepted 840 l/s service and the BOOT operating term still ahead.

Taweelah carries the owner-level operating statement

ACWA's current Taweelah RO profile supplies the later-stage statement missing at Rabigh 4: commercial operations from Q1 2024. That supports an operating classification for the 200 MIGD plant. Earlier ACWA reporting also recorded phased production and a Group 2 commercial-operation certificate before the current full-project status.

The public marine file still ends at proposed intake and outfall layouts and bid-stage flow assumptions in the environmental appendices. A repair tender would need final route, depth, joint, diffuser and condition data before contractors could price work on the sea connection.

South Tarawa closed its civil works before service improved

South Tarawa provides the long view. ADB records its three ocean-outfall civil package complete in August 2018, testing and commissioning in the second quarter of 2019, and whole-project physical completion at the end of that year.

ADB's later completion and independent evaluation reports found mixed water-quality and service outcomes after the outfalls were built. Operating capability then depended on maintenance, staffing, monitoring, network connections and repeated performance after handover.

Contractor performance and commercial operation remain separate

The World Bank's desalination guidance describes the water purchase agreement as the contract that fixes delivered quantity, quality, pressure and tariff, while some operating performance becomes verifiable only after commissioning. Its PPP risk-allocation guidance similarly places minimum output, quality, efficiency and environmental tests before permission to enter commercial operation.

Rabigh 4 therefore has a reported full-capacity EPC test with a stated energy-performance result. No public owner or offtaker acceptance record has followed. Its public classification remains commissioning until SWPC or another contractually accountable party confirms commercial operation; final marine geometry, hydraulic acceptance and receiving-water compliance also remain unpublished.