Waterway Works
Holt Lock Extends Its Weekend Navigation Pattern to December
IMWO original navigation calendar; source: USACE Mobile District bulletin 26-129, 22 October 2026.
Holt Lock is scheduled to reopen for weekend navigation on 31 October, followed by five-day construction closures through an estimated 18 December. The revised access programme accompanies permanent monolith repairs.
The revised weekly access programme
The US Army Corps of Engineers has revised the navigation programme around permanent repairs to a damaged monolith at Holt Lock on Alabama's Black Warrior-Tombigbee Waterway. Bulletin 26-129, issued on 22 October, schedules continuous closure until 06:00 on 31 October, followed by a five-day closure and two-day opening pattern through an estimated 18 December. [1] Each weekly opening is scheduled from 06:00 Saturday to 06:00 Monday. The intervening five days are reserved for construction. The notice prints its times as CDT, including the period after the November clock change; operators need the district's confirmation of the operating clock when booking a passage. [1] The district's June bulletin had anticipated a 27 October-6 November phase using the five-day/two-day arrangement. The October revision moves the start of that arrangement to 31 October and extends its expected duration into December. Traffic plans based on the June programme need the revised weekly openings. [1, 2]
Arrival timing controls passage exposure
A two-day opening provides 48 scheduled passage hours in a 168-hour week. That is 28.6% of calendar time before accounting for lockage cycles, vessel queues and the way arrivals cluster around reopening. The access pattern concentrates demand at the same time that construction has exclusive use of the lock during the working week. For a tow approaching near Monday's cutoff, a missed passage can roll into the following weekend. Dispatch planning therefore needs an arrival margin, upstream and downstream holding arrangements, and the current lockmaster's instructions. A simple five-day allowance in an itinerary obscures the importance of the arrival day and hour.
Evidence conclusion
Permanent repairs follow the monolith failure
In its April engineering account, Mobile District traced the problem to new and worsening cracks observed in May 2024 in the riverside wall monolith. Water entered machinery spaces, and the district closed the lock on 22 June 2024. An interim steel bulkhead sealed the culvert intake, allowing the lock to reopen on 2 October that year. [3] Permanent repair began on 12 January 2026. The first phase included rows of large post-tensioned anchors, with drilling and reaming of core holes followed by anchor installation and stressing. The district described subsequent work involving additional anchor rows and mass concrete, with dedicated closure periods for the more intensive repairs. [3] The current navigation bulletin governs access during that repair programme. Its December endpoint is an estimate. Contractors arranging deliveries by water and operators routing cargo through the lock should use the issued passage windows in their vessel plans and refresh them against later district bulletins.
Outstanding evidence
- Later district bulletins and lockmaster passage instructions
- District confirmation of the operating clock after the November change
- Tow arrival margin, queues and available holding areas
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 3
- USACE Mobile District, navigation bulletin 26-129, issued 22 October 2026, NTNI 215380 USACE Mobile District, 22 October 2026
- USACE Mobile District, navigation bulletin 26-75, 9 June 2026 USACE Mobile District, 9 June 2026
- USACE Mobile District, permanent repair account, 28 April 2026 USACE Mobile District, 28 April 2026