Contract Completion

Wesleyville-Brookfield dock contract is marked complete

Published 12 August 2026 Updated 13 August 2026 Publisher IMWO Region Americas Confidence Confirmed
Official Brookfield floating docks and mooring details showing concrete anchor blocks, mooring chains, mooring plates and connection hardware

Fisheries and Oceans Canada / Meridian Engineering; official C2-00084 drawing C9 of 10, issued for tender in August 2021

Granite Management's ten-week DFO contract combined Wesleyville floating-dock removal and boardwalk repair with a new Brookfield access, crib, dredging, gangway and two-dock system. Public Accounts mark the contract completed at CAD 393,285, but do not close the physical asset or supply-chain record.

Public Accounts closes the contract status

CanadaBuys identifies Granite Management, the contract number, award date and CAD 392,533.75 reported value. The official invitation, specification and drawings set out the two-site scope, ten-week term, geometry and price-form quantities. Public Accounts lists CAD 393,285 as the amount contracted, provides expenditure fields and marks the contract complete. Neither record supplies accepted physical quantities or names lower tiers.

Wesleyville and Brookfield carry different work scopes

The award title names Wesleyville, while the bid package splits execution between Wesleyville and Brookfield. The first workfront is demolition and retained-asset repair; the second combines land access, drainage, hard-bottom crib founding, environmental control, dredging and floating infrastructure. Award-title-only tracking loses the Brookfield workfront and the marine package most relevant to dock, mooring, dredging, timber and civil suppliers.

Evidence conclusion

Physical completion details await owner records

The 2021-22 Public Accounts apply note f, defined as a contract completed in the current year. This supports completed contract classification with Confirmed confidence. CanadaBuys reports CAD 392,533.75, while Public Accounts reports CAD 393,285 in its amount-contracted and expenditure fields. No cited record explains the CAD 751.25 difference, so the figures describe separate source fields. Price-form quantities, including 40 m3 of treated-timber cribwork, two floating docks, one gangway and 95 CMPM of dredging, remain tender baselines until owner acceptance, as-built records and final bathymetry are published.

Outstanding evidence

  • Owner completion and acceptance certificates
  • Final Brookfield bathymetry and accepted dredging quantity
  • As-built crib, road, culvert and shoreline-protection records
  • Installed dock, gangway, chain and concrete-anchor inventory
  • Wesleyville demolition and boardwalk-repair acceptance
  • Environmental closeout and harbour reopening
  • Named dredging, timber, floating-dock, mooring and civil lower tiers
  • CAD 751.25 ledger reconciliation