Lake-port EPC evidence
CCECC signed Rumonge's USD 26.453 million EPC contract
Burundi's implementing agency signed the Rumonge Port design-and-build contract with China Civil Engineering Construction Corporation on 27 July 2026 for USD 26.453 million. Contract 1893998 establishes the prime EPC relationship and procurement identity. Notice to proceed, site possession, approved design programme, supervision appointment, mobilised marine plant and first physical works remain unpublished.
The signed contract supersedes the procurement-plan estimate
Contract 1893998 controls CCECC's prime role, signature date, committed amount and procurement method. P174814 metadata controls programme status and closing date. The May 2025 procurement plan is a pre-award baseline, while the appraisal defines intended functions rather than final EPC design. No cited source establishes notice to proceed, approved design, mobilisation, executed quantities or lower-tier awards as of 5 August 2026.
Rumonge remains at award stage pending mobilisation
Rumonge combines lake access, pier geometry, cargo transfer, border controls and buildings in one package. Procurement data can establish who holds the prime contract and at what value, but it cannot show whether surveys, design reviews, temporary works, water-level assumptions or site access are ready. Those gates determine when a nominal award becomes an executable marine package.
Evidence conclusion
Design approval and site access control the first works
Contract 1893998 reports USD 26,452,721.36, above the procurement plan's USD 21 million estimate and the appraisal's earlier USD 20 million intervention envelope. The three values have different dates and scope bases, so their difference is not proof of an overrun. Rumonge should remain at award stage until a dated owner, lender, engineer or contractor record establishes the execution clock, site possession, approved baseline and first works. Lower-tier tracking should then separate supervision, design, survey, piling, marine plant, buildings and local civil works.
Outstanding evidence
- Effective notice to proceed, site possession and execution-clock start
- Supervision consultant and accepted design-review programme
- Bathymetry, geotechnical baseline and design water levels
- Pier foundations, dredging need, shore protection and temporary works
- Marine plant, survey, piling and local civil subcontractors
- First certified physical quantities and approved programme update
- Commissioning, acceptance and operating handover
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 4
- World Bank contract 1893998 for BI-BI-MOF-493818-CW-RFB World Bank Projects and Operations API, Contract signed 27 July 2026; record reviewed 5 August 2026
- P174814 procurement plan including the Rumonge Port EPC package World Bank, Revised 18 May 2025
- Great Lakes Trade Facilitation and Integration Project appraisal document World Bank, 9 June 2022 approval baseline
- Great Lakes Trade Facilitation and Integration Project P174814 API record World Bank, Current project record reviewed 5 August 2026