Contract Close-out

Petit-Cap's Berlin-wall contract still lacks acceptance evidence

Published 6 August 2026 Publisher IMWO Region Americas Confidence Confirmed
Close-up of structure 403 Berlin wall construction, cofferdam works and dredging activity at Petit-Cap

IMWO artist's impression accompanying this evidence brief

CanadaBuys records Landco Construction Ltd. under CAD 3,083,763.87 contract CW2335551 for Petit-Cap structure 403. The package partially demolishes the timber-crib marginal wharf, dredges the harbour basin, builds a new Berlin-wall marginal wharf, reinstates electrical services and manages cofferdam and environmental controls. The eight-month contract ended on 4 July 2024, while accepted completion and final quantities remain unpublished.

An eight-month contract term ended while four interfaces remained unverified

CanadaBuys controls the contractor, CAD 3,083,763.87 total, award date, eight-month term and tendered structure 403 scope. The tender and archive pages clarify the Berlin-wall, dredging, electrical and environmental workstreams but do not prove as-built delivery. No cited official record supplies accepted quantities, commissioning, named lower tiers, final payment, defects close-out or return to use. The illustration is editorial scope context only.

Structure 403 needs an as-built and close-out bundle

Berlin-wall alignment and embedment, dredged basin geometry, electrical commissioning and environmental close-out each require different acceptance evidence. The contract expiry proves the recorded delivery window, not that the cofferdam was removed, the dredging was accepted, the wall passed inspection or the harbour returned to service.

Evidence conclusion

Structure 403 acceptance remains the completion threshold

Outstanding evidence

  • Berlin-wall alignment, embedment and structural inspection
  • Pre- and post-dredge surveys and accepted quantities
  • Cofferdam removal and environmental close-out
  • Electrical-service testing and commissioning
  • Dredging, steel, electrical and survey lower tiers
  • Final account, owner acceptance and harbour reopening