Jetty mobilisation
Preah Sihanouk's inspectorate jetty has an award, not a mobilisation record
Taing Cheng Oing Construction & Import Export signed SCMFP FiA/CW-03 on 9 March 2026. The approved design defines a 2,226.71 m2 reinforced-concrete boat-mooring and landing platform, 3.5-4.0 m wide, within the existing Preah Sihanouk fisheries inspectorate. ADB reports a financed amount of 472,336.05 but not its currency or the full contract value, and no cited source proves mobilisation.
A named contractor replaced the procurement estimate, but the financial record remains incomplete
ADB's award workbook controls the contractor, signing date and source-reported financed amount while omitting currency and full contract value. The procurement plan controls the USD 750,000 estimate. The safeguard report controls approved design and land impacts, not mobilisation. The VMS building is a separate package.
The award fixes the contractor while leaving delivery mechanics open
A small fisheries jetty still carries marine foundations, durable concrete, tide, vessel-access, public-road and operating-site interfaces. Delivery status depends on the notice to proceed, construction method, work programme, supervision chain, access controls and first verifiable marine works.
Evidence conclusion
Separate the jetty package, the VMS building and the two value measures
The December 2025 plan's USD 750,000 estimate is not the contract value. The operational procurement workbook's 472,336.05 is an ADB-financed amount with no exposed currency or full contract total. The safeguard document proves design footprint and public-land status, not construction. CW-03 should be tracked through notice to proceed, foundations, marine concrete, access management, building fit-out, vessel trials and owner acceptance, while CW-01 Lot 3 remains separate.
Outstanding evidence
- Notice to proceed and site possession
- Full contract value and currency
- Foundation, piling and concrete method
- Contractor and supervision mobilisation
- Shared-road and operating-site access plan
- Progress certificates and environmental records
- Vessel trials and owner acceptance
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 4
- ADB operational procurement database record for SCMFP FiA/CW-03 Asian Development Bank, Contract signed 9 March 2026; database as of 30 June 2026
- Social due diligence report for VMS and Marine FiAI subprojects Asian Development Bank, Published July 2026
- Sustainable Coastal and Marine Fisheries Project procurement plan Asian Development Bank, Version 4 dated 5 December 2025
- Sustainable Coastal and Marine Fisheries Project 53261-001 Asian Development Bank, Current project page reviewed 5 August 2026