SADDN first water connects Pacific supply to Radomiro Tomic

Published 13 July 2026 Updated 15 July 2026 Editorial responsibility IMWO Region Americas Confidence Confirmed
Aerial construction view of the SADDN reverse-osmosis desalination plant beside the Caleta Viuda coast

Techint Engineering & Construction

SADDN has moved from its 2022 BOOT award through a defined 1.3 km submarine system, coastal energization, intake-tower installation and high-head conveyance to first desalinated water at Radomiro Tomic. The complete route is connected, while accepted 840 l/s service, marine reliability and supply to all three divisions remain unverified.

What changed

Codelco's 30 June 2022 board record authorized the BOOT contract with the Marubeni-Transelec consortium and identified more than USD 1 billion of investment, marine works, 840 l/s initial capacity and more than 160 km of conveyance. Techint's June 2023 record confirms Aguas Horizonte issued the EPC order to proceed. By June 2024 the auxiliary pier, coastal sump and offshore pipe welding were active; the October update documented underwater blasting, trench work, diving, intake pipes and brine return. Codelco's September 2024 commissioning-counterpart procurement assigns design, construction, commissioning, start-up and 20-year operation to the developer while preserving owner assurance and later Codelco operation of the distribution system. Techint reported coastal energization in August 2025, first intake-tower installation in November, a 940 m Loa River HDD in December, and near-complete reservoir works in March 2026. Its 23 June first-water report explicitly describes construction, hydraulic testing and progressive interface validation rather than final acceptance or commercial operation.

Why it matters

This is a rare public evidence chain from Pacific intake works to a reservoir above 3,000 m. First water proves route continuity, but operations depend on accepted product-water quality, continuous three-stage pumping, power reliability, intake and brine-return availability, distribution to Radomiro Tomic, Chuquicamata and Ministro Hales, and the handoff between Aguas Horizonte's BOOT operation and Codelco's distribution responsibility.

Decision read

What remains open

SADDN has crossed a harder threshold than a plant-only commissioning milestone: water travelled through the connected Pacific intake, treatment, power, pumping and 160 km conveyance chain to the high-altitude reservoir. The remaining threshold is operational, not visual. First arrival, 87% progress, coastal energization, an installed intake tower, a completed river crossing and a nearly complete reservoir do not individually establish accepted 840 l/s service. That claim still requires marine availability, compliant water quality, continuous high-head pumping, all-division distribution, owner acceptance and BOOT service evidence.

Next watchpoints

  • Codelco declaration of full commercial operation
  • Rated 840 l/s flow and water-quality acceptance
  • Marine intake, submarine pipe, and brine-return performance
  • High-head pumping and electrical reliability across the full route
  • Sustained delivery to all three Northern District divisions

Knowledge context

Related knowledge topics

Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.