Waterway Works
Potter Reserves the Night for Dredging
IMWO original engineering diagram; source: USACE St.Louis District
USACE schedules nightly 17:00-07:00 closures around Potter at the lower Chain of Rocks canal. The pipeline dredge works around the clock, while the published traffic closure protects a concentrated production period.
A fourteen-hour closure around the plant
The US Army Corps of Engineers has scheduled nightly river closures around dredge Potter at the lower Chain of Rocks canal, Upper Mississippi River mile 184.1. Notice 215399 sets out approximately six nights of maintenance dredging beginning on or about 26 October, with closures from 17:00 to 07:00 to support production. [1] The published programme gives the dredge and its tenders, barges and pipeline a 24-hour, seven-day operating pattern. Removed material is pumped outside the navigation channel through a pontoon or self-floating pipeline that may cross the channel. Potter can be contacted on marine channels 13 or 16. [1]
Passage coordination is part of the production cycle
The nightly closure occupies 14 hours. The remaining 10 hours sit within the plant's continuing 24-hour operation, so a tow approaching in daylight still needs the dredge's passage instructions and the position of its pipeline. The notice's purpose is to provide a concentrated working period near the plant. In a pipeline operation, a vessel passage can require a pause, pipe handling and restoration of the working arrangement. Grouping passage demand into coordinated periods can reduce repeated interruptions to the same dredging cut. Actual passage capacity depends on the workfront and traffic queue.
Evidence conclusion
Match the pipeline arrangement to the assignment
In its August 2026 season account, St. Louis District describes Potter's normal side-casting pontoon pipeline and planned use of flexible pipe for selected assignments requiring placement at specific locations. It records a three-watch crew arrangement supporting continuous operation. [2] The district's 2024 maintenance account also records a quick-release system added to the disposal pipeline to improve handling safety. [3] The Chain of Rocks notice allows either pontoon or self-floating pipeline. The applicable passage arrangement therefore depends on the pipe actually deployed and its position that day. Dispatchers should obtain the current closure instruction before releasing a tow into the work area and allow for the queue at reopening. The published six-night duration is approximate; later instructions and the restored channel condition determine the next operating plan.
Outstanding evidence
- Current closure instruction and Potter passage coordination
- Pipeline position, queue and arrival timing at reopening
- Later programme changes and restored channel condition
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 3
- St. Louis District NTNI 215399, Upper Mississippi River mile 184.1 USACE St.Louis District, 23 October 2026
- Dredge Potter returns for 2026 dredging season USACE St.Louis District, 28 August 2026
- Potter 2024 season: pump and pipeline maintenance USACE St.Louis District, 21 June 2024