Location
UAE / Middle East
Performance record
Block A's 60 MIGD commissioning is the first public operating milestone for Hassyan's 180 MIGD Phase 1, but the available evidence is insufficient to establish full-plant reliability or post-handover performance. This record separates the confirmed entry into service and documented intake-outfall design basis from the remaining acceptance, uptime, water-quality, and diffuser-monitoring evidence.
Evidence boundary: the cited sources establish a defined milestone or observation, not certification or a post-handover performance conclusion.
UAE / Middle East
Block A commissioned; sustained operation and full-plant acceptance not established
Block A commissioning evidence
13 July 2026
Scope and limits
Owner statements available on 13 July 2026 confirm Block A commissioning and the published delivery schedule. The project structure and ESIA also define the marine design basis. No independent records establish uptime, product-water compliance, outfall performance, environmental monitoring results, final completion or acceptance of the remaining blocks.
Confirmed
Still unverified
Metric observations
Entry into service is confirmed for Block A, but public uptime, availability, outage, and maintenance evidence remains insufficient for a reliability conclusion.
The first commissioning milestone and the remaining delivery sequence are public; final completion, acceptance, and defect-closeout evidence remain outstanding.
The ESIA establishes the intake-outfall and diffuser design basis, but post-commissioning marine monitoring results remain unavailable publicly.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
The project record provides delivery scope and participants. The related brief provides dated project context and unresolved technical questions.
Open project record Read related intelligence brief Explore performance evidenceThe record is limited to the cited public evidence and does not confer certification, ranking, warranty, safety or environmental approval, recognition, or procurement endorsement.
Open performance evidence Review methodology Submit a correction