Dredging evidence
Lower Yarra's completed programme does not close AMA's current contract
AMA is the named supplier on a current AUD 1.93985 million Lower Yarra contract and the named Campaign C contractor. A separate annual report says the 2022-24 programme finished in 2024; that does not prove contract closeout, accepted quantities or final depth.
Campaign C provides unusually specific contractor and reach attribution
Buying for Victoria identifies the supplier, contract reference, displayed value basis, start and Current status. Parks Victoria attributes the programme to AMA and describes Campaign C's operating geography. Melbourne Water's annual-report page and PDF report the 2022-24 completion and future-funding position. AMA publishes its own award statement. Dredging Today is secondary support for the Campaign B sequence and pipe-placement method; BMT supplies separate study context.
Contract status, campaign delivery and programme completion are three clocks
The Lower Yarra combines a live procurement row, dated river-work controls and a later programme-level completion statement. Commercial and operating decisions become unreliable if the portal total is treated as final spend, the end of a navigation-control period as owner acceptance, or the annual report's programme completion as administrative contract closure.
Evidence conclusion
The missing layer is measured and accepted delivery
The Victorian procurement portal names Australasian Marine Associates on ITS2-00225, displays a fixed AUD 1,939,850 total, records 8 September 2021 as start date and labels the contract Current. Parks Victoria then names AMA for Campaign C across six dredging reaches and two material-discharge areas from 13 March to 24 June 2024. The 2024-25 Yarra Strategic Plan annual report says the 2022-24 programme was completed in 2024 and that about AUD 1.2 million per year remains necessary, with a bid submitted for a next two-year programme. None of those records publishes accepted bathymetry, campaign quantities, final account, contract closeout or a new funding award.
Outstanding evidence
- Executed ITS2-00225 term, extension history and administrative closeout
- Pre- and post-dredge survey and accepted functional depth by reach
- Measured quantity and in-river placement record by campaign
- Named dredger, support craft, pipeline, survey and monitoring lower tiers
- Water-quality results and environmental closeout
- Certified payments, variations and final account
- Decision on the next two-year funding bid and successor procurement
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 6
- ITS2-00225 Lower Yarra River maintenance dredging contract Buying for Victoria, Current contract row reviewed 10 August 2026
- AMA News - Yarra River maintenance dredging award Australasian Marine Associates, Current company page reviewed 10 August 2026
- Notice to River Users issued 13 June 2024, including Campaign C controls Parks Victoria, 13 June 2024
- Yarra Strategic Plan Annual Report 2024-25 Melbourne Water and Yarra Strategic Plan partners, 2024-25 annual report
- Campaign B maintenance dredging on Yarra River underway Dredging Today, 5 April 2022
- Specialist dredging advisory - Lower Yarra River Dredge Study BMT, Current service page reviewed 10 August 2026