Contract Change
Barranquilla's COP 150.97bn award is now a COP 241.68bn live contract
SECOP II records a COP 150.967 billion initial award for Barranquilla's access-channel maintenance dredging and a later modified contract value of COP 241.685 billion with a 31 December 2026 current end date. The selected consortium is legally split 70% Caribbean Region Water Conservancy Engineering SAS, 20% Panamerican Dredging and 10% CFD Ingenieria SAS. Cormagdalena documented active dredging and 80.7% execution at 31 March; accepted quantities, completion and final cost remain unpublished.
The contract now carries three dated commercial states
SECOP II controls the initial award, current contract ledger and legal consortium composition. Cormagdalena controls dated field-progress and vessel statements. The owner's multi-year dredging totals are not a contract-specific quantity ledger. No cited source proves completion, allocates physical work among members or names a lower-tier subcontractor. The image is an official visit aboard Xin Hai Ma and evidences project activity, not acceptance or member-level performance.
The published member chain stops before field allocation
The initial award, the owner's March progress snapshot and the later SECOP modification answer different questions. COP 150.967 billion is the award baseline; COP 198.564 billion was the value cited with 80.7% execution at 31 March; COP 241.685 billion is the later current contract ledger. Calling the last figure an overrun or final account would outrun the evidence because the variation instruments, measured bill and close-out remain unpublished.
Evidence conclusion
Consortium shares establish legal participation only
Outstanding evidence
- Signed modification instruments and priced variation schedule
- Current dredger, owner and operating party
- Pre- and post-dredge surveys and accepted channel depth
- Contract-specific measured dredged volume and disposal ledger
- Physical work allocation and lower-tier appointments
- Completion certificate, final navigation release and final account
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 6
- SECOP II electronic contract CO1.PCCNTR.6778468 Agencia Nacional de Contratacion Publica / Datos Abiertos Colombia, Updated 11 May 2026
- SECOP II procurement process CO1.BDOS.6340037 Agencia Nacional de Contratacion Publica / Datos Abiertos Colombia, Awarded 18 September 2024
- SECOP II provider group 728030099 Agencia Nacional de Contratacion Publica / Datos Abiertos Colombia, Group registered 21 August 2024
- Barranquilla channel dredging progress aboard Xin Hai Ma Cormagdalena, 13 June 2025
- Hang Jun 6008 mobilisation for Barranquilla access channel Cormagdalena, 5 February 2026
- Three years of continuous 10-metre navigation draft Cormagdalena, 9 April 2026