Kitchener Drain rehabilitation and Samatay-Hamoul pumping stations
Participation
Requires review
Participation checked
Drain and bank works reported in execution in January 2026; Samatay-Hamoul evaluation complete with award order in preparation in September, followed by an October procurement review
Kitchener rehabilitation combines drain dredging and bank protection with separately procured pumping works. Dated MWRI progress records and the original environmental controls support a reach-level handover linking repaired banks, excavation limits and pumping interfaces.
Agricultural drain rehabilitation, bank protection and pumping stations
Phase
Construction / Confirmed
Last checked
4 November 2026
Coverage
Related sectors
Agricultural drain rehabilitation, bank protection and pumping stations is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
Ministry of Water Resources and Irrigation (MWRI); drainage implementation: Egyptian Public Authority for Drainage Projects (EPADP); pumping implementation: Mechanical and Electrical Department (MED)
Work-package contractors are unspecified in the cited MWRI progress accounts.
Contract route
EBRD 49417; ECEPP PP1 32012619; ECEPP addendum 41669641. PP1 was advertised as an open two-stage works procurement for replacement stations at Samatay, km57.5, and Hamoul, km2.5. The indexed 9 December 2025 addendum extends Stage 2 to 13 January 2026, without a time or timezone in that text. The September 2026 official account reports completed evaluation and preparation of the award order. Current participation requires the controlling package record.
Execution window
The January 2026 drain-work progress account, September 2026 evaluation/award-preparation account and October 2026 procurement review describe different workstreams and dates. Pump commissioning and programme completion await package-specific records.
Works package
EBRD project 49417: dredging and drainage rehabilitation, replacement or rehabilitation of pumping stations, Omar Bek diversion and flow/water-quality monitoring. MWRI's January 2026 account reports two dredging/weed-removal packages and two bank-rehabilitation packages in execution, with stone pitching and a retaining wall. PP1 Samatay-Hamoul is a distinct pumping package.
Marine interfaces
The drain discharges toward the Mediterranean. MWRI's 8 November 2025 account discusses lower Kitchener at Al Khashaa weir and drains ending at Lake Burullus. It identifies storm-period sea-level rise as a constraint at drain outfalls, raising upstream and subsidiary-drain levels. Station and channel design needs the relevant receiving-water boundary for each connection.
Commercial evidence boundary
The October 2018 environmental summary calls for dredging methods that avoid undermining banks and saturated spoil loading on bank crests. EBRD's July 2019 appraisal describes possible processed-material reuse and separate disposal. Pricing depends on the issued excavation envelope, processing area, material acceptance and disposal provisions, and access beside the bank repairs.
Evidence gap
What remains unverified
Outstanding evidence
Reach-specific bank-protection drawings, dredging limits and post-work cross-sections
Issued Samatay and Hamoul interfaces, award records and commissioning provisions
Dredged-material classification, processing areas and authorised reuse or disposal routes