NEP Completes Two Wells for Its Expansion-Store Appraisal

Published 30 October 2026 Publisher IMWO Region Europe Confidence Confirmed
IMWO diagram. NEP March 2026 expansion concept: CS006 would include four injection wells and CS007 three; completed BC39-1 and BC37-1 appraisal wells inform evaluation, planned 2027 FEED after concept selection and planned 2028 FID.

IMWO original development-concept diagram based on NEP March 2026 statement and 27 October 2026 appraisal update.

NEP has completed its two-well appraisal across CS006 and CS007. The results now inform expansion capacity, well duties and a programme through concept selection, planned 2027 FEED and a planned 2028 investment decision.

Two wells complete the appraisal campaign

Northern Endurance Partnership has completed its two-well appraisal campaign across Southern North Sea storage licences CS006 and CS007. Its 27 October update identifies the completed wells as C43/30-2, known as BC39-1, and C44/27-3, known as BC37-1. Evaluation and characterisation will continue through 2026 and 2027, with front-end engineering design planned for 2027 after concept selection and a final investment decision planned for 2028. [1] The programme combines the wells with geophysical surveys, environmental assessment and offshore studies. The new results feed into an expansion concept whose well count and subsea connections were set out in NEP's March 2026 System Development Statement. That document makes the expansion capacity and scope contingent on the appraisal analysis and an additional investment decision. [2] The March concept envisages four injection wells for CS006, covering the BC40 and BC39 storage sites, with a connecting pipeline to Endurance. CS007 would cover BC37 and BC36, with three injection wells. These are the development statement's expected configurations. [2, section 4.2]

Well duties shape the future subsea system

The well configurations give the appraisal work an infrastructure consequence. The usable injection rates and pressure limits determine the flow each storage system can receive. Detailed design then needs the well duties, connection pressures and operating cases that the pipelines, manifolds and controls must accommodate. A change in the usable storage envelope can change the equipment duty and allocation of flow. NEP's June account of the first well reported around 500 metres of sealing rock above a 250-metre Bunter sandstone interval at BC39. It described the results as preliminary and said the collected data would support further technical appraisal. Those thicknesses concern BC39; the October completion announcement brings the second well and wider studies into the evaluation programme. [3]

Evidence conclusion

Evaluation leads into concept selection

For offshore contractors and engineering suppliers, the next consequential development is the selected expansion configuration: the receiving stores, injection duties, subsea connections and their installation sequence. The March statement also identifies potential later work on legacy-well remediation, detailed design, permitting and licensing. [2] This expansion has its own development and investment sequence alongside the existing Endurance construction programme. NEP's July construction announcement describes the separate 149-kilometre offshore pipeline from Teesside. The expansion-store programme now has completed appraisal wells and a stated route through evaluation, concept selection, FEED and investment decision. [1, 4]

Outstanding evidence

  • Combined appraisal interpretation and selected expansion configuration
  • Injection duties, operating pressures and subsea connection scope
  • Concept-selection outcome,2027 FEED and 2028 investment decision