Contracts

Agate wins Absecon outfall and beach-access works

Published 1 September 2026 Publisher IMWO Region Americas Confidence Confirmed
Absecon outfall award milestone diagram separating Agate's confirmed appointment from an issued notice to proceed, installed works and drainage acceptance

IMWO original Absecon outfall award milestone diagram from the August release and July procurement; later delivery dates and acceptance remain unconfirmed

USACE Philadelphia District has awarded Agate Construction Co. a USD 19.695 million Absecon Island outfall package. The 27 August announcement identifies seven repair or extension locations in three municipalities and a separate Ventnor vehicle ramp, within the island's coastal storm risk management programme.

Three municipalities share the awarded workfronts

Four outfall locations lie in Atlantic City, one in Ventnor and two in Margate. Ventnor's New Haven Avenue ramp is a separate access item. The July W912BU26BA026 solicitation describes pipe-support demolition, repair and pile driving, with additional outfall and access works offered through separate bid options. The award announcement does not provide the final exercised-option schedule or quantities at each outlet.

Drainage and beach reinstatement meet at the outlet

The works connect existing stormwater conveyance with a wave-exposed receiving beach. Pipe support, excavation access and reinstatement therefore interact with the coastal protection profile. The April programme factsheet's five-outfall Margate manifold is an existing network, whereas this award lists seven repair locations across three municipalities. Their different counting bases cannot establish an increase in network size.

Evidence conclusion

Notice to proceed defines the delivery clock

The correct July procurement allows 480 calendar days from notice to proceed. An August award date does not start that clock, and the announcement supplies neither the issued notice date nor confirmation of an unchanged final duration. Agate's appointment is confirmed; mobilisation, installed repair quantities, restored drainage performance and acceptance remain later milestones. Lower-tier appointments and a final works account are also undisclosed.

Outstanding evidence

  • Issued notice to proceed and workfront programme
  • Exercised options and outlet-specific quantities
  • Pipe-support installation and beach reinstatement
  • Accepted drainage service and final account