Mubarak Al-Kabeer Phase I EPC signed with CCCC at RMB 28.43bn
Kuwait's Ministry of Public Works and CCCC signed the Phase I EPC for Mubarak Al-Kabeer Port in December 2025. CCCC values the water-transport contract at RMB 28.43 billion. The award is confirmed; the executing subsidiary, detailed marine scope, subcontractors, mobilisation, construction quantities and completion schedule are not.
The project now has a signed parent-company EPC
KUNA records the 22 December 2025 EPC signing between Kuwait's Ministry of Public Works and CCCC. CCCC's exchange filing reports the RMB 28.43 billion value and water-transport classification. KUNA's February 2026 committee report describes continuing government follow-up without physical progress. The 2025 KUNA records distinguish the earlier study, design and pre-execution services contract from the later EPC. The Ministry yearbook supplies historical Stage One Part 2 context only. A CCCC executing subsidiary, downstream marine subcontractor, mobilisation, current quantity and acceptance evidence remain unpublished.
The filing names CCCC at parent-company level but no delivery subsidiary
The 22 December 2025 government record and CCCC's first-quarter 2026 filing agree on the Ministry of Public Works as client, CCCC as the Phase I EPC contractor and RMB 28.43 billion as the disclosed contract value. Neither record names the executing subsidiary, designer, dredging contractor, quay contractor, equipment supplier or local subcontractors. Detailed allocation across design, dredging, reclamation, quay works, equipment and logistics therefore remains unpublished.
Evidence conclusion
Notice to proceed, issued scope and first quantities remain unpublished
The Phase I EPC is signed and CCCC reports RMB 28.43 billion. Kuwait's February 2026 committee release records government oversight but no notice to proceed, marine mobilisation or installed quantities. Historical Ministry quantities belong to an earlier Stage One Part 2 baseline and are not the 2025 EPC bill of quantities. The current public record also omits the issued scope and schedule, executing subsidiary, designers, subcontractors, marine fleet and certified progress.
Outstanding evidence
- Contract notice to proceed and contractual completion date
- Issued scope and treatment of inherited Stage One assets
- CCCC executing subsidiary and engineering-design responsibility
- Dredging, reclamation, quay, marine plant, equipment and local subcontract awards
- Environmental approvals, dredged-material route and hydrographic controls
- Certified physical progress, depth acceptance, equipment commissioning and first operation
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 6
- Kuwait and China sign Mubarak Al-Kabeer Port EPC contract Kuwait News Agency (KUNA), 22 December 2025
- Key operational data for the first quarter of 2026 China Communications Construction Company Limited / Hong Kong Stock Exchange, 28 April 2026
- Kuwait PM chairs ministerial committee meeting on major development projects Kuwait News Agency (KUNA), 19 February 2026
- Kuwait and Chinese officials visit Mubarak Al-Kabeer Port Project Kuwait News Agency (KUNA), 17 April 2025
- Study, design and pre-execution services contract signing Kuwait News Agency (KUNA), 16 February 2025
- Mubarak Al-Kabeer Port Stage One Part 2 historical scope Kuwait Ministry of Public Works, Statistical yearbook page reviewed 1 August 2026