Three Registers for Cost, Measurement and Payment

Published 15 October 2026 Publisher IMWO Section Methods
Three registers through the project. Use common project, contract, package and event identifiers. Original IMWO diagram.

IMWO original editorial graphic

Three linked registers carry cost, quantities and payment status through a marine project. Field definitions, a month-by-month cash-flow example and an omission calculation give teams a practical starting point for their own contract records.

The Price of Winning / Series contents

Registers through the project

Use the same project, contract and work-package identifiers across these registers. Each entry needs a document reference, date, author and version. State currency and tax treatment. Enter deadlines from the actual contract and applicable rules.

Register 1: cost and risk

FieldRequired entry
Bid basisScope, quantity, source-data dates, tax, currency and exchange assumptions
ProductionPlant, material, pumping or haul distance, cycle and time basis
Revenue quantityMeasurement rules, conversion assumptions, re-siltation and overdepth
Cost structureMobilisation, installation, people, plant, fuel, maintenance and demobilisation
Price revisionPrevious and revised price; resource or method change; evidence and approval
Risk allocationTrigger, controlling party, clause, cost and time treatment
FundingExpected and delayed receipts, facility, drawdown conditions and peak date
Term mismatchUpstream/downstream pricing, payment, standby, reduction and termination

Register 2: changes and measurement

FieldRequired entry
Event identifierLink to package, plant log, survey and notice
InstructionIssuer, authority, date, original text and confirmation
ScopeAddition, omission, resequencing, condition or interface; original scope retained
QuantitySubmitted, agreed and disputed; datum, boundary and calculation reference
RateOriginal or new basis, adjustments and each party's position
TimeCalendar period, vessel-days and operating hours separately
Cost changeIncurred, saved, continuing and additional costs
Next decisionInformation owner, assessor, decision-maker, date and escalation

Register 3: payments and retention

FieldRequired entry
Amount identifierContract, package, period and application or invoice
Original amountPrincipal, tax, deductions and currency
Primary statusUnmeasured; unpriced; certified not due; due unpaid; disputed; retention
Split itemsSeparate amounts where status differs; avoid double counting
DatesSubmission, complete information, measurement, certification, due and receipt
Due-date basisClause, applicable rule, triggering event and period
DisputeIssue, competing amounts, undisputed part, notice and next process
Receipt allocationPrincipal, tax, interest or other allocation; remaining balance
RetentionBasis, accumulated amount, cap, condition, eligibility and release
Downstream linkRelated supplier account, due amount and actual payment

Cash-flow example: every monthly movement

Amounts below are CNY million. Each of four construction months produces 20 of billable work and costs 17 in cash. Mobilisation costs 4 in month 0. Progress receipts are 95% of value; total retention is 4. There is no advance, tax, interest or defect expenditure. Cash movements occur at month end.

MonthCostReceipt: one-month lagCumulative balanceReceipt: two-month lagCumulative balance
040-40-4
1170-210-21
21719-190-38
31719-1719-36
41719-1519-34
5019419-15
6004194

Both sequences receive 76 in progress payments. Later release of 4 retention brings total receipts to 80 against 72 cost, leaving 8 before finance and tax. Peak funding is 21 or 38. Intra-month peaks may differ.

Omission example

Fixed cost: CNY 10 million. Variable cost: CNY 20 per cubic metre. Original quantity: one million cubic metres. Original average cost: CNY 30 per cubic metre.

With 600,000 cubic metres remaining and all fixed costs retained, total cost is CNY 22 million, averaging CNY 36.67 per cubic metre. Actual omissions require an assessment of cancellable commitments, changed material and resources.

Use the records through the job

Register 1 supports bid approval. Register 2 records instructions, quantities and valuation. Transfer recognised amounts into register 3, allocate receipts and update balances. At each review, focus on unresolved entries, the responsible person and the next date. Retain prior versions.