Energy Terminals
ACME Duqm CBM: Masirah Marine is the reported installation lead
ACME's Duqm export package is a four-buoy Conventional Buoy Mooring for refrigerated green ammonia. EIL holds the offshore engineering consultancy, Bluewater the CBM agreement and Straatman the delivered control package. An industry source identifies Masirah Marine as the most likely selected installation contractor. Masirah's Oman portfolio supports the attribution through relevant buoy, anchoring, pipeline, diving, survey and construction-barge experience, although no public ACME-, Bluewater- or Duqm-specific award confirms it. Bluewater's ACME release describes system delivery, while the company's wider literature records experience delivering and installing CBM systems. That leaves Masirah's main-contract or subcontract position unresolved. Masirah's fleet page lists twin-screw tugs rather than ASD units, and an Imodco/SBM Offshore study calls for two ASD tugs during Khareef connection operations. The tug provider remains an undisclosed part of the offshore spread.
An industry source points to Masirah Marine
EIL's official presentation defines a consultancy role through March 2027. Bluewater's award names a four-buoy CBM scheduled for January 2026 delivery and 2027 use, while its support-services brochure documents wider CBM installation experience. Straatman confirms delivered and pre-commissioned controls. An industry source dated 5 August 2026 identifies Masirah Marine as the most likely installer. Masirah's official pages support the capability match without naming ACME, Bluewater or Duqm. Its fleet page lists construction barges and twin-screw tugs but no ASD or anchor-handling vessel. Imodco identifies two ASD tugs for Khareef connection work. Award, package boundary, tug provider, mobilisation and acceptance remain undisclosed.
The offshore contract boundary remains unresolved
Masirah's published capabilities align with the physical work: buoy and SPM installation, subsea anchoring, chain work, pipelines, commercial diving, survey and crane-barge support. Bluewater also has its own history of CBM installation and installation engineering, so the available material does not establish whether Masirah holds the full offshore package, works under Bluewater or carries a narrower diving and marine-construction subcontract. The published Masirah fleet does not cover the two-ASD-tug requirement identified for Khareef connection work. Contracting party, scope, named tugs, anchors and chains, hoses, PLEM, export pipeline, ROV support and acceptance remain open.
Evidence conclusion
Masirah's role awaits contract and mobilisation records
Green Hydrogen and Chemicals SPC is the ACME-owned project vehicle, and EIL holds the INR 61 million offshore engineering consultancy through March 2027. Bluewater's project-specific agreement covers delivery of the four-buoy CBM, with Straatman supplying the control and hydraulic-release package. Exact-project imagery places assembled equipment at APT Global's Ras Al Khaimah yard, while Resinex cooperation is acknowledged without a defined package. An industry source identifies Masirah Marine as the most likely physical installer. Its official portfolio supports that assessment, but the absence of a project award, notice to proceed, named vessel or mobilisation record limits the attribution to Reported. Bluewater's installation history also leaves several possible commercial structures: Masirah may contract with ACME, subcontract to Bluewater or perform a narrower marine-construction scope. The two ASD tugs required during Khareef connection work remain a separate undisclosed charter or subcontract interface.
Outstanding evidence
- Project-specific confirmation of Masirah Marine's appointment, contracting route, scope and mobilisation date
- EIL offshore engineering deliverables and March 2027 completion status
- Anchor, chain, floating-hose, submarine-hose and PLEM suppliers
- Export-pipeline, shore-crossing and subsea-valve package boundaries
- Named installation vessel, crane barge, diving, ROV and survey allocation
- Provider, charter route and mobilisation plan for the two ASD tugs required during Khareef connection operations
- Navigation-aid and emergency-release commissioning
- Yara tanker compatibility and first ammonia transfer
- Any current Phase 2 equity participation or exercise of Scatec's retained option
- H1 2027 first molecule kept separate from first export
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 32
- Investor Presentation - Annual Results FY 2024-25 Engineers India Limited, 30 May 2025
- Contract award ACME and Bluewater - Ammonia CBM Bluewater Energy Services, 22 May 2025
- Support Services for Single Point Mooring Systems Bluewater Energy Services, Company capability brochure reviewed 13 August 2026
- Mooring buoy system for green ammonia Straatman, 12 February 2026
- Bluewater Oman mooring and buoy-control delivery thread Straatman, 12 February 2026
- Duqm's Green Hydrogen Initiative Special Economic Zone at Duqm, 2 December 2025
- CBM vs CALM for large ammonia cargo transfer: the Oman case Imodco / SBM Offshore, October 2025
- APT Global Marine and Offshore Engineering APT Global, Current company and facility page reviewed 3 August 2026
- Support and Mooring Buoys Resinex, Current product page reviewed 3 August 2026
- SLG 80 MW green hydrogen systems delivered to ACME Oman Shuangliang Hydrogen, 3 March 2026
- Sungrow signs 320 MW green-hydrogen equipment agreement for Oman Sungrow, 18 January 2025
- Sungrow electrolysers for ammonia production in Oman and Kenya Ammonia Energy Association, citing Sungrow Hydrogen, 29 March 2026
- Khimji Ramdas Shipping delivers critical logistics for green-ammonia project Khimji Ramdas Shipping, 2 July 2025
- Arctech and ACME partner for the 175 MWp Duqm tracker package Arctech India, 31 May 2025
- Oman is central to our global decarbonization mission: ACME Group Energy Oman Magazine, 28 January 2026
- Signing ceremony of Oman's green hydrogen projects Oman Ministry of Energy and Minerals, 15 March 2023
- Scatec first quarter report 2023 Scatec ASA, 5 May 2023
- Yara and ACME signed a binding agreement for supply of green ammonia Yara International, 1 March 2024
- ACME Duqm project partner and study map ACME Group, October 2022
- Darkocean Geostar completes offshore geotechnical fieldwork for Duqm green-ammonia plant Darkocean, 2 May 2025
- Green Ammonia Project, Duqm Gulf Testing Lab, 2024 project listing; reviewed 1 August 2026
- Global Investors Sign Major Agreements in Duqm Special Economic Zone at Duqm, 9 June 2026
- ACME green-ammonia tank-foundation project and BGD concrete milestone BGD Value Contractor project-team and company disclosure, Project record reviewed 4 August 2026
- DM-water tank filling and hydrotest preparation at Duqm Towell Engineering Group / UNISCO project-team disclosure, July 2026
- Liquid-ammonia custody-transfer metering skid for the 300 MTPD project Cryogenic OGS project-team disclosure, Project record reviewed 4 August 2026
- Unnamed CALM buoy and PLEM fabrication update APT Global project-team disclosure; ACME exclusion control, July 2026
- Oman CALM buoy and PLEM HAZOP naming OQ, Monobuoy and CCCC Rhizome Energy; separate-project exclusion control, 2025 post reviewed 4 August 2026
- Diving and operations capabilities Masirah Marine, Current company page reviewed 7 August 2026
- Marine construction capabilities Masirah Marine, Current company page reviewed 7 August 2026
- Equipment and plant division Masirah Marine, Current fleet page reviewed 7 August 2026
- Clients and key projects Masirah Marine, Current portfolio reviewed 7 August 2026
- Masirah International corporate profile Masirah International Technical and Marine Services LLC, Current corporate profile reviewed 7 August 2026