Coastal Award Boundary
Grenada signs two Soubise coastal-protection lots while Marquis remains unawarded
Grenada now has two signed Soubise coastal-protection contracts worth USD 5,747,307.91 in aggregate. General Earth Movers-UEM Inc. holds Lot 1 South and Construction and Industrial Equipment holds Lot 2 North. The safeguards design still shows a separate Marquis Lot 3, for which no current award record was found.
Two Soubise works contractors are now confirmed
World Bank records 1885376 and 1885375 control the Lot 1 and Lot 2 suppliers, values, signature and no-objection dates. The Government RFB controls the original procurement identity and tender-stage duration. The final ESIA and ESMP define the three-lot design, Alpha Engineering & Design role, detailed quantities, anticipated plant, material-source assumptions and safeguards. They do not prove mobilisation or final supplier selection.
The awarded boundary stops before Marquis Lot 3
The award split creates two adjacent delivery fronts around an existing gabion wall, boat access, a fishing facility, a river mouth and the Eastern Main Road. Lot 2's design basis anticipates barges, tugs, a heavy-lift crane barge, divers and survey control, while both lots depend on armour grading, quarry logistics, traffic management and nearshore environmental controls. Treating the corridor as one undifferentiated award would hide both the contractor interface and the still-open Marquis package.
Evidence conclusion
Soubise mobilisation and lower tiers remain unconfirmed
The legal supplier gap is closed for Soubise and remains open for Marquis. World Bank records show both Soubise contracts signed on 27 April 2026 and report no-objection on 18 May, but contain no notice to proceed, site possession, mobilisation, subcontractor, installed quantity, completion or acceptance field. The ESMP names Alpha Engineering & Design as design and supervision consultant and identifies Mon Rush and Mt. Hartman only as potential material sources. Its detailed scope says the new Lot 1 boat ramp is 26 m, while the equipment summary says 20 m; an accepted contract drawing or bill of quantities is required before using either as the contractual baseline.
Outstanding evidence
- Notice to proceed, site possession and current completion date for each Soubise lot
- Final allocation and interface management between Lot 1 South and Lot 2 North
- Accepted boat-ramp length and final Lot 1 bill of quantities
- Any contract award, redesign or deferral for Marquis Lot 3
- Armour-rock and aggregate purchase orders, grading and quarry test results
- Barge, tug, heavy-lift crane barge, excavator, diving and RTK-GPS providers
- Toe excavation, river-outfall, drainage and overtopping design controls
- Fishing-facility, small-boat, community and Eastern Main Road access
- Turbidity, waste, sargassum and sensitive-nearshore monitoring
- As-built surveys, accepted quantities, completion and post-storm performance
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 6
- Contract record 1885376 for Soubise Lot 1 South World Bank, Contract signed 27 April 2026; no-objection 18 May 2026
- Contract record 1885375 for Soubise Lot 2 North World Bank, Contract signed 27 April 2026; no-objection 18 May 2026
- Request for bids for Soubise/Marquis coastal-protection works Government of Grenada Procurement Portal, 18 August 2025
- Final environmental and social management plan for Soubise and Marquis Government of Grenada / Alpha Engineering & Design, 2 September 2025
- Final environmental and social impact assessment for Grenville, Soubise and Marquis Government of Grenada / Alpha Engineering & Design, 2 September 2025
- Grenada Resilience Improvement Project P175720 World Bank, Current project page reviewed 7 August 2026